Tenement: E08-1393

View on Landtracker Maps (logon required)

Extracted from MTO on 11-Jul-2025 01:13, last changed 04-Jul-2025.

Tenement Summary

Identifier:E 08/1393-IType:Exploration Licence
Status:LiveDistrict:ASHBURTON M.F.
Lodged:KARRATHAArea:7 BL
Purposes:Term:5 Years (Extended)
Markout:Received:09-May-2003 09:35
Commence:22-Mar-2006 Expiry:21-Mar-2026

Holders

Company NameSharesTotal Shares
FMG PILBARA PTY LTD100100

Applicants on Receival

Company NameSharesTotal Shares
CULLEN EXPLORATION PTY LIMITED100100

Relationships

Relationship TypeDealingDealing StatusTenementTenement Status
Section 67Conversion 419365FinalisedM 08/502-ILive
Amalgamation (Same Holder)Amalgamation 484168GrantedP 47/1647-IDead
Section 67Conversion 576848RecordedM 47/1591-NDead
Section 67Conversion 576909RecordedM 08/529Pending

Shires

Shire NameShire NumberStartArea
ASHBURTON SHIRE25009-May-2003 7.00000 BL

Conditions

#VerTextStartEnd
11All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion.22-Mar-2006
21All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Industry and Resources (DoIR). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DoIR.22-Mar-2006
31All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program.22-Mar-2006
41Unless the written approval of the Environmental Officer, DoIR is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations.22-Mar-2006
51The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment.22-Mar-2006
61The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-
  • the grant of the Licence; or
  • registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer.
22-Mar-2006

Endorsements

Cond #VerTextStartEnd
11All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion.22-Mar-2006
21All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Industry and Resources (DoIR). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DoIR.22-Mar-2006
31All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program.22-Mar-2006
41Unless the written approval of the Environmental Officer, DoIR is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations.22-Mar-2006
51The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment.22-Mar-2006
61The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-
  • the grant of the Licence; or
  • registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer.
22-Mar-2006

Dealings

TypeNumberDetails
Copy Document315678Lodged:15:35 18 March 2009ISSUED:15:35 18 March 2009
Partial Surrender - Compulsory315679Lodged:15:35 18 March 2009Section:Section 65 (1)(a)Surrendered Blocks:HAMERSLEY RANGE 2336 y HAMERSLEY RANGE 2337 f, l, m, q, r, s HAMERSLEY RANGE 2408 d, j, k, o, p, u HAMERSLEY RANGE 2409 f, l, m, q, r, s HAMERSLEY RANGE 2410 qSurrendered Total:20 BL.REGISTERED:23:59:59 21 March 2009Surrendered area to be released 08:30:00 28/04/2009 under Section 65(5)Surrendered area released 08:30:00 28/04/2009 under Section 65(5)
Partial Surrender - Compulsory343068Lodged:15:10 18 March 2010Section:Section 65 (1)(b)Surrendered Blocks:HAMERSLEY RANGE 2336 d, j, k, o, p HAMERSLEY RANGE 2408 n HAMERSLEY RANGE 2409 o, p, t, uSurrendered Total:10 BL.REGISTERED:Midnight 21 March 2010Surrendered area to be released 08:30:00 14/04/2010 under Section 65(5)Surrendered area released 08:30:00 14/04/2010 under Section 65(5)
Forfeiture360124Initiated:22/11/2010 for non-compliance with expenditure conditionsRECORDED:08:30 22 November 2010Notice Issued:Regulation 50 Notice sent 22/11/2010 for non-compliance with expenditure conditions pursuant to Reg 21 & 22.Compliance Date:22/12/2010FINALISED:Order by Minister on 21 January 2011 that E 08/1393-I be Penalty Imposed
Fine363871Fine in respect to:Forfeiture Process 360124Fine reason:Non-compliance with expenditure obligationsPenalty amount:$2,205.00Notification date:21/01/2011Due date:25/02/2011Pursuant to:Section 96A(5)RECORDED:21 January 2011PAYMENT RECEIVED:28 January 2011Receipt Number:89412Amount:$2,205.00Remaining balance:$0.00FINALISED:28 January 2011
Copy Document367919Lodged:11:50 21 March 2011ISSUED:11:50 21 March 2011
Extension / Renewal of Term367920Lodged:11:50 21 March 2011Applied For Period:2 YearsRECORDED:11:50 21 March 2011GRANTED:28 June 2011Granted Period:2 YearsTerm Extended To:21/03/2013
Application to Amend367936Lodged:15:25 21 March 2011Amending:AddressFrom:CULLEN EXPLORATION PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 8638, PERTH BUSINESS CENTRE, WA, 6849To:CULLEN EXPLORATION PTY LTD, C/- TENEMENT ADMINISTRATION SERVICES PTY LTD, LEVEL 2, 326 HAY STREET, EAST PERTH, WA, 6004RECORDED:15:25 21 March 2011
Extension of Time372284Lodged:15:40 24 May 2011Type:Exemption from ExpenditureRECORDED:15:40 24 May 2011APPROVED:17:00 25 May 2011
Forfeiture374315Initiated:22/06/2011 for non-compliance with expenditure conditionsForm 5 lodged outside prescribed periodRECORDED:10:22:42 20 June 2011Notice Issued:Regulation 50 Notice sent 22/06/2011 for non-compliance with expenditure conditions pursuant to Reg 21 & 22.Compliance Date:27/07/2011FINALISED:Order by Minister on 12 August 2011 that E 08/1393-I be Penalty Imposed
Fine379129Fine in respect to:Forfeiture Process 374315Fine reason:Non-compliance with expenditure obligationsPenalty amount:$90.00Notification date:16/08/2011Due date:16/09/2011Pursuant to:Section 96A(5)RECORDED:12 August 2011PAYMENT RECEIVED:17 August 2011Receipt Number:98677Amount:$90.00Remaining balance:$0.00FINALISED:17 August 2011
Extension of Time399398Lodged:08:21 13 June 2012Type:Stat DecRECORDED:08:21 13 June 2012APPROVED:12:54:11 13 June 2012Extension of time until 28 June 2012 to lodge statutory declaration in support of Appln 397692 for exemption from expenditure condition for the year ending 21 March 2012
Extension / Renewal of Term419332Lodged:11:55:59 20 March 2013Applied For Period:2 YearsRECORDED:11:55:59 20 March 2013GRANTED:08 October 2013Granted Period:2 YearsTerm Extended To:21/03/2015
Conversion419365New Tenement:M 08/502Application Date:15:30 19 Mar 2013Section:S67Discontinued 00:00 12 October 2016 due to Portion not included in grant of Mining Lease in respect to M 08/502
Application to Amend419873Lodged:15:30 27 March 2013Amending:AddressFrom:Residential : CULLEN EXPLORATION PTY LIMITED, SAME AS CORRESPONDENCE and Correspondence :CULLEN EXPLORATION PTY LIMITED, C/- TENEMENT ADMINISTRATION SERVICES PTY LTD, LEVEL 2, 326 HAY STREET, EAST PERTH, WA, 6004To:Residential : CULLEN EXPLORATION PTY LIMITED, ADDRESS NOT PROVIDED and Correspondence :CULLEN EXPLORATION PTY LIMITED, ACQUISITIONS AND TENEMENTS DEPARTMENT, PO BOX 3379 HAY STREET, EAST PERTH, WA, 6004RECORDED:15:30 27 March 2013
Application to Amend419874Lodged:15:30 27 March 2013REJECTED:15:30 27 March 2013
Extension / Renewal of Term463322Lodged:14:44:09 04 March 2015Applied For Period:1 YearsRECORDED:14:44:09 04 March 2015GRANTED:29 June 2015Granted Period:1 YearsTerm Extended To:21/03/2016
Partial Surrender - Voluntary480266Lodged:15:25 15 January 2016Surrendered Blocks:HAMERSLEY RANGE 2409 g, h, j, nSurrendered Total:4 BL.REGISTERED:15:25 15 January 2016
Extension / Renewal of Term483321Lodged:15:30:10 16 March 2016Applied For Period:1 YearsRECORDED:15:30:10 16 March 2016GRANTED:27 May 2016Granted Period:1 YearsTerm Extended To:21/03/2017
Amalgamation484168Lodged:15:25 31 March 2016Amalgamating:Whole of P 47/1647-ISituated within:External boundaries of E 08/1393-IGranted 23/11/2016 in respect to P 47/1647-I
Excess Tonnage493187Lodged:09:30 26 August 2016RECORDED:09:30 26 August 2016GRANTED:10:56:49 05 September 2016Approved for an additional 505 tonnes.
Extension / Renewal of Term502751Lodged:11:08:32 17 March 2017Applied For Period:1 YearsRECORDED:11:08:32 17 March 2017GRANTED:13 June 2017Granted Period:1 YearsTerm Extended To:21/03/2018
Application to Amend505354Lodged:16:11:56 27 April 2017Amending:Address (Including DTC Details)From:FMG PILBARA PTY LTD, LEVEL TWO, 87 ADELAIDE TERRACE, EAST PERTH, WA, 6004To:FMG PILBARA PTY LTD, ACQUISITIONS AND TENEMENTS DEPARTMENT, PO BOX 3379 HAY STREET, EAST PERTH, WA, 6004RECORDED:16:11:56 27 April 2017
Excess Tonnage510835Lodged:10:00 19 July 2017RECORDED:10:00 19 July 2017GRANTED:14:04:36 24 July 2017Additional 322 tonnes
Caveat514683Lodged:15:50 15 September 2017Caveat Type:Consent CaveatCaveator:CULLEN EXPLORATION PTY LIMITEDShares Caveated:100/100 shares FMG PILBARA PTY LTDRECORDED:15:50 15 September 2017
Extension / Renewal of Term525389Lodged:11:26:29 13 March 2018Applied For Period:1 YearsRECORDED:11:26:29 13 March 2018GRANTED:21 May 2018Granted Period:1 YearsTerm Extended To:21/03/2019
Extension / Renewal of Term549496Lodged:08:43:10 18 March 2019Applied For Period:1 YearsRECORDED:08:43:10 18 March 2019GRANTED:22 May 2019Granted Period:1 YearsTerm Extended To:21/03/2020
Partial Surrender - Voluntary570108Lodged:14:14:57 13 January 2020Surrendered Blocks:HAMERSLEY RANGE 2336 t, uSurrendered Total:2 BL.REJECTED:14:14:57 13 January 2020
Extension / Renewal of Term574434Lodged:08:30 18 March 2020Applied For Period:1 YearsRECORDED:08:30 18 March 2020GRANTED:22 May 2020Granted Period:1 YearsTerm Extended To:21/03/2021
Conversion576848New Tenement:M 47/1591Application Date:14:23:33 24 Apr 2020Section:S67
Conversion576909New Tenement:M 08/529Application Date:14:23:33 24 Apr 2020Section:S67
Application to Amend587109Lodged:10:26:02 25 September 2020Amending:Address (Including DTC Details)From:Principal Place of Business : FMG PILBARA PTY LTD, ACQUISITIONS AND TENEMENTS DEPARTMENT, PO BOX 3379 HAY STREET, EAST PERTH, WA, 6004 and DTC :FMG PILBARA PTY LTD, ACQUISITIONS AND TENEMENTS DEPARTMENT, PO BOX 3379 HAY STREET, EAST PERTH, WA, 6004To:Principal Place of Business : FMG PILBARA PTY LTD, PO BOX 3379 HAY STREET, EAST PERTH, WA, 6004, xxxxxxxxxxxxxxxxxx@fmgl.com.au and DTC :FMG PILBARA PTY LTD, ACQUISITIONS AND TENEMENTS DEPARTMENT, PO BOX 3379 HAY STREET, EAST PERTH, WA, 6004, xxxxxxxxxxxxxxxxxx@fmgl.com.auRECORDED:10:26:02 25 September 2020
Application to Amend587934Lodged:15:58 08 October 2020Amending:Address (Including DTC Details)From:FMG PILBARA PTY LTD, PO BOX 3379 HAY STREET, EAST PERTH, WA, 6004, xxxxxxxxxxxxxxxxxx@fmgl.com.auTo:FMG PILBARA PTY LTD, ACQUISITIONS AND TENEMENTS DEPARTMENT, PO BOX 3379 HAY STREET, EAST PERTH, WA, 6004, xxxxxxxxxxxxxxxxxx@fmgl.com.auRECORDED:15:58 08 October 2020
Extension / Renewal of Term617216Lodged:11:19:18 08 March 2021Applied For Period:1 YearsRECORDED:11:19:18 08 March 2021GRANTED:21 May 2021Granted Period:1 YearsTerm Extended To:21/03/2022
Extension / Renewal of Term642686Lodged:10:54:46 04 March 2022Applied For Period:1 YearsRECORDED:10:54:46 04 March 2022GRANTED:18 May 2022Granted Period:1 YearsTerm Extended To:21/03/2023
Excess Tonnage665575Lodged:13:15:47 15 December 2022RECORDED:13:15:47 15 December 2022GRANTED:12:31 12 January 2023Additional 8,166 tonnes
Extension / Renewal of Term669703Lodged:13:01:34 24 February 2023Applied For Period:1 YearsRECORDED:13:01:34 24 February 2023GRANTED:18 May 2023Granted Period:1 YearsTerm Extended To:21/03/2024
Extension / Renewal of Term697436Lodged:09:19:16 27 February 2024Applied For Period:1 YearsRECORDED:09:19:16 27 February 2024GRANTED:01 May 2024Granted Period:1 YearsTerm Extended To:21/03/2025
Extension / Renewal of Term727399Lodged:08:30 05 March 2025Applied For Period:1 YearsRECORDED:08:30 05 March 2025GRANTED:19 May 2025Granted Period:1 YearsTerm Extended To:21/03/2026

Payments

TypeYearReceipt DateReceipt No.MR LodgedAmountRental AreaEffective DateAmt DueDiscrepancy
Rental202627-Mar-2025 10788472$5,488.007 BL15-Jan-2016 $5,488.00$0.00
Rental202522-Mar-2024 10532628$5,229.007 BL15-Jan-2016 $5,229.00$0.00
Rental202403-Apr-2023 10344461$4,977.007 BL15-Jan-2016 $4,977.00$0.00
Rental202323-Mar-2022 10250736$4,739.007 BL15-Jan-2016 $4,739.00$0.00
Rental202223-Mar-2021 10189440$4,305.007 BL15-Jan-2016 $4,305.00$0.00
Rental202117-Mar-2020 52062431451$4,207.007 BL15-Jan-2016 $4,207.00$0.00
Rental202018-Mar-2019 92052806791$3,969.007 BL15-Jan-2016 $3,969.00$0.00
Rental201913-Mar-2018 8095087329$3,745.007 BL15-Jan-2016 $3,745.00$0.00
Rental201821-Feb-2017 MT-210010946964-DD$3,623.207 BL15-Jan-2016 $3,623.20$0.00
Rental201704-Mar-2016 MT-210010534415-DD$3,504.207 BL15-Jan-2016 $3,504.20$0.00
Rental201604-Mar-2015 MT-210010237377-DD$5,366.9011 BL21-Mar-2010 $5,366.90$0.00
Rental201524-Mar-2014 MT-210010168128-DD$5,230.5011 BL21-Mar-2010 $5,230.50$0.00
Rental201420-Mar-2013 MT-210010098825-DD$5,128.2011 BL21-Mar-2010 $5,128.20$0.00
Rental201322-Mar-2012 06-107554PERTH$2,634.5011 BL21-Mar-2010 $2,634.50$0.00
Rental201221-Mar-2011 91391PERTH$2,813.2511 BL21-Mar-2010 $2,813.25$0.00
Rental201126-Mar-2010 77126PERTH$2,030.3811 BL21-Mar-2010 $2,030.38$0.00
Rental201006-Apr-2009 (REFUND) 62864PERTH$3,542.0021 BL21-Mar-2009 $3,719.10$0.00
Rental201024-Mar-2009 62864PERTH$7,261.10
Rental200918-Mar-2008 49269PERTH$4,514.5141 BL22-Mar-2006 $4,514.51$0.00
Rental200814-Mar-2007 35232PERTH$4,307.0541 BL22-Mar-2006 $4,307.05$0.00
Rental200721-Mar-2006 22270PERTH$346.6841 BL22-Mar-2006 $3,815.46-$0.18
Rental200709-May-2003 7932KARRATHA$3,468.60

Expenditure

YearForm 5 TypeMin ExpdExp Lodged DateTotal ExpdExemp NoExemp LodgedExemp AmtExemp StatusOutcome DateExploration ActivitiesMining ActivitiesAboriginal SurveyRentAdministrationProspectingStrike Through
2026$70,000.00false
2025$70,000.0029-Apr-2025 $170,970.00$152,848.00$0.00$0.00$6,579.00$11,543.00$0.00false
2024$70,000.0030-Apr-2024 $229,144.00$215,076.00$0.00$0.00$6,287.00$7,781.00$0.00false
2023$70,000.0017-May-2023 $81,543.00$61,778.00$0.00$0.00$6,027.00$13,738.00$0.00false
2022$70,000.0013-May-2022 $78,021.05$58,453.05$0.00$0.00$5,568.00$14,000.00$0.00false
2021$70,000.0014-May-2021 $98,486.00$89,016.00$0.00$0.00$5,470.00$4,000.00$0.00false
2020$70,000.0014-Apr-2020 $143,053.20$113,979.00$0.00$0.00$5,232.00$23,842.20$0.00false
2019$70,000.0014-May-2019 $70,971.00$58,923.00$0.00$2,222.00$4,895.00$4,931.00$0.00false
2018$70,000.0017-May-2018 $247,689.00$235,438.00$0.00$2,817.00$4,661.00$4,773.00$0.00false
2017$70,000.0012-May-2017 $103,967.00$44,326.00$0.00$41,212.00$4,429.00$14,000.00$0.00false
2016$70,000.0029-Apr-2016 $95,959.00$67,497.00$0.00$7,728.00$6,734.00$14,000.00$0.00false
2015$70,000.0008-May-2015 $153,892.00$123,118.00$0.00$0.00$6,151.00$24,623.00$0.00false
2014$70,000.0014-May-2014 $139,283.00$110,893.00$0.00$0.00$6,211.00$22,179.00$0.00false
2013$50,000.0016-May-2013 $56,064.00$42,461.00$0.00$0.00$3,603.00$10,000.00$0.00false
2012$50,000.0017-May-2012 $8,886.0039769217-May-2012 $50,000.00Granted18-Jul-2012 $4,497.00$0.00$0.00$3,490.00$899.00$0.00false
2011$30,000.0024-May-2011 $13,433.0037220824-May-2011 $30,000.00Granted15-Aug-2011 $8,681.00$0.00$0.00$2,514.00$2,238.00$0.00false
2010$31,500.0007-May-2010 $9,453.0034661110-May-2010 $31,500.00Refused22-Nov-2010 $141.00$0.00$0.00$7,737.00$1,575.00$0.00false
2009$41,000.0012-May-2009 $9,498.0032071713-May-2009 $41,000.00Granted15-Jul-2010 $1,328.00$0.00$0.00$6,617.00$1,553.00$0.00false
2008$41,000.0029-Apr-2008 $79,639.00$60,516.00$0.00$0.00$5,850.00$13,273.00$0.00false
2007$41,000.0018-May-2007 $43,643.00$29,865.00$0.00$0.00$5,578.00$8,200.00$0.00false

Native Title Referrals

Referred to Native Title DateReferral TypeCurrent StatusProcedureDetailsObjectionsWater CommentsDetermination AreasClaimsRepresentative Area Bodies
20-Jun-2016 Tenement AmalgamationExpedited Procedure : Native Title Cleared - Expedited AppliesExpedited Procedure2016-07-082016-11-08CLEARED - Expedited Applies2016-11-2222.7 HA224357S1163932E113km NW'ly of ParaburdooPuutu Kunti Kurrama People and Pinikura People #1 and #2(WCD2015/003)WC2005/004WAD126/2005trueWCD2015/003BOTHNo12PilbaraYamatji Marlpa Aboriginal Corporation
05-Sep-2005 Tenement ApplicationIn Progress