Tenement: E04-2508

View on Landtracker Maps (logon required)

Extracted from MTO on 07-Jul-2025 00:59, last changed 26-Jun-2025.

Tenement Summary

Identifier:E 04/2508Type:Exploration Licence
Status:LiveDistrict:WEST KIMBERLEY M.F.
Lodged:ONLINEArea:47 BL
Purposes:Term:5 Years (Extended)
Markout:Received:03-Jan-2018 09:42
Commence:08-May-2018 Expiry:07-May-2028

Holders

Company NameSharesTotal Shares
DREADNOUGHT EXPLORATION PTY LTD100100

Applicants on Receival

Company NameSharesTotal Shares
IRONRINGER (TARRAJI) PTY LTD100100

Shires

Shire NameShire NumberStartArea
DERBY-WEST KIMBERLEY SHIRE280003-Jan-2018 47.00000 BL

Conditions

#VerTextStartEnd
11The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any exploration activities on Meda Location 15 (Yampi Defence Area CHL/105418).08-May-2018 03-Sep-2019
1Consent to explore on Meda Location 15 (Yampi Defence Training Area) granted subject to:03-Sep-2019
21The Australian Government not guaranteeing access to the Commonwealth Land.03-Sep-2019
31The licensee obtaining the relevant approvals required under the Land Acquisitions Act 1989 (Cth).03-Sep-2019
41If deed of access is granted, exploration activities being limited to those specified in the deed.03-Sep-2019
51Any proposed future mining activities, being subject to separate approval required under the Lands Acquisition Act 1989 (Cth).03-Sep-2019
62Exploration and prospecting disturbances, excluding supporting infrastructure, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 12 months after completion of the activity unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety.09-Jun-2025
61All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety.03-Sep-2019 08-Jun-2025
71All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program.03-Sep-2019
81Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations.03-Sep-2019
92The construction and operation of the project and measures to protect the environment to be carried out in accordance with the document titled:
  • (PoW Reg ID 80671) "Dreadnought Resources Environmental Management Plan Tarraji-Yampi Project" Version 1.3, dated 2 August 2019 signed by P Chapman, and retained on Department of Mines, Industry Regulation and Safety File No. EARS-POW-80671 as Doc ID 6841916;
  • (Pow Reg ID 87726) "Dreadnought Resources Environmental Management Plan Tarraji-Yampi Project Version 1.4" dated 10 August 2020 submitted by Dean Tuck, and retained on Department of Mines, Industry Regulation and Safety File No. EARS-POW-87726 as Doc ID 7613427                         
27-Aug-2020
91The construction and operation of the project and measures to protect the environment to be carried out in accordance with the document titled:
  • (PoW Reg ID 80671) "Dreadnought Resources Environmental Management Plan Tarraji-Yampi Project" Version 1.3, dated 2 August 2019 signed by P Chapman, and retained on Department of Mines, Industry Regulation and Safety File No. EARS-POW-80671 as Doc ID 6841916                          
02-Oct-2019 26-Aug-2020
101All supporting infrastructure for exploration and prospecting including core yards, laydowns, camps, and access tracks (excluding drill lines), being rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Rehabilitation being required by the earlier of 12 months from the infrastructure being no longer required to support exploration, or 12 months from the relevant programme of work expiring, unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety.09-Jun-2025
111The tenement holder must maintain appropriate records of exploration/prospecting activities, and associated rehabilitation undertaken, in order to demonstrate compliance with all conditions and environmental management and rehabilitation practice commitments. These records to be made available to the Department upon request.09-Jun-2025
121All exploration and prospecting operations to comply with the environmental management and rehabilitation practice commitments provided in the approved programme of work.09-Jun-2025

Endorsements

Cond #VerTextStartEnd
11The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any exploration activities on Meda Location 15 (Yampi Defence Area CHL/105418).08-May-2018 03-Sep-2019
1Consent to explore on Meda Location 15 (Yampi Defence Training Area) granted subject to:03-Sep-2019
21The Australian Government not guaranteeing access to the Commonwealth Land.03-Sep-2019
31The licensee obtaining the relevant approvals required under the Land Acquisitions Act 1989 (Cth).03-Sep-2019
41If deed of access is granted, exploration activities being limited to those specified in the deed.03-Sep-2019
51Any proposed future mining activities, being subject to separate approval required under the Lands Acquisition Act 1989 (Cth).03-Sep-2019
62Exploration and prospecting disturbances, excluding supporting infrastructure, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 12 months after completion of the activity unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety.09-Jun-2025
61All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety.03-Sep-2019 08-Jun-2025
71All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program.03-Sep-2019
81Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations.03-Sep-2019
92The construction and operation of the project and measures to protect the environment to be carried out in accordance with the document titled:
  • (PoW Reg ID 80671) "Dreadnought Resources Environmental Management Plan Tarraji-Yampi Project" Version 1.3, dated 2 August 2019 signed by P Chapman, and retained on Department of Mines, Industry Regulation and Safety File No. EARS-POW-80671 as Doc ID 6841916;
  • (Pow Reg ID 87726) "Dreadnought Resources Environmental Management Plan Tarraji-Yampi Project Version 1.4" dated 10 August 2020 submitted by Dean Tuck, and retained on Department of Mines, Industry Regulation and Safety File No. EARS-POW-87726 as Doc ID 7613427                         
27-Aug-2020
91The construction and operation of the project and measures to protect the environment to be carried out in accordance with the document titled:
  • (PoW Reg ID 80671) "Dreadnought Resources Environmental Management Plan Tarraji-Yampi Project" Version 1.3, dated 2 August 2019 signed by P Chapman, and retained on Department of Mines, Industry Regulation and Safety File No. EARS-POW-80671 as Doc ID 6841916                          
02-Oct-2019 26-Aug-2020
101All supporting infrastructure for exploration and prospecting including core yards, laydowns, camps, and access tracks (excluding drill lines), being rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Rehabilitation being required by the earlier of 12 months from the infrastructure being no longer required to support exploration, or 12 months from the relevant programme of work expiring, unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety.09-Jun-2025
111The tenement holder must maintain appropriate records of exploration/prospecting activities, and associated rehabilitation undertaken, in order to demonstrate compliance with all conditions and environmental management and rehabilitation practice commitments. These records to be made available to the Department upon request.09-Jun-2025
121All exploration and prospecting operations to comply with the environmental management and rehabilitation practice commitments provided in the approved programme of work.09-Jun-2025

Dealings

TypeNumberDetails
Application to Amend569871Lodged:14:25:47 08 January 2020Amending:Address (Including DTC Details)From:Principal Place of Business : IRONRINGER (TARRAJI) PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947, xxxxxxxxx@austwidemining.com.au, xxxxxxx400 and DTC :IRONRINGER (TARRAJI) PTY LTD, AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947, xxxxxxxxx@austwidemining.com.au, xxxxxxx400To:Principal Place of Business : IRONRINGER (TARRAJI) PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxxxx997 and DTC :IRONRINGER (TARRAJI) PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxxxx997RECORDED:14:25:47 08 January 2020
Application to Amend570552Lodged:16:08:51 20 January 2020Amending:NameFrom:IRONRINGER (TARRAJI) PTY LTDTo:DREADNOUGHT (KIMBERLEY) PTY LTDRECORDED:16:08:51 20 January 2020
Application to Amend619331Lodged:15:13:10 31 March 2021Amending:NameFrom:DREADNOUGHT (KIMBERLEY) PTY LTDTo:DREADNOUGHT EXPLORATION PTY LTDRECORDED:15:13:10 31 March 2021
Application to Amend621259Lodged:16:26:18 27 April 2021Amending:Address (Including DTC Details)From:DREADNOUGHT EXPLORATION PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxxxx997To:DREADNOUGHT EXPLORATION PTY LTD, MCMAHON MINING TITLE SERVICES PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxxxx997RECORDED:16:26:18 27 April 2021
Application to Amend674467Lodged:13:34:44 27 April 2023Amending:Address (Including DTC Details)From:DREADNOUGHT EXPLORATION PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxxxx997To:DREADNOUGHT EXPLORATION PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 6301, EAST PERTH, WA, 6892, xxxx@mmts.net.au, xxxxxxxxxxx997RECORDED:13:34:44 27 April 2023
Extension / Renewal of Term674658Lodged:09:31:15 01 May 2023Applied For Period:5 YearsRECORDED:09:31:15 01 May 2023GRANTED:10 August 2023Granted Period:5 YearsTerm Extended To:07/05/2028
Partial Surrender - Voluntary682519Lodged:13:29:36 31 July 2023Surrendered Blocks:BROOME 408 l, m, n, q, r, s, w, x BROOME 409 l, r, s, y, z BROOME 410 v, w BROOME 479 c, h, j, n, o BROOME 480 c, j, w BROOME 481 p, u, z BROOME 482 b, l, m, q, r, v, w BROOME 553 b, j, o, p BROOME 554 a, bSurrendered Total:39 BL.REGISTERED:13:29:36 31 July 2023
Partial Surrender - Voluntary697385Lodged:15:07:24 26 February 2024Surrendered Blocks:BROOME 408 y BROOME 409 q, w, x BROOME 480 d, p BROOME 481 d, e, j, k, v BROOME 482 a, f, gSurrendered Total:14 BL.REGISTERED:15:07:24 26 February 2024
Partial Surrender - Voluntary709334Lodged:15:14:37 12 July 2024Surrendered Blocks:BROOME 408 o, p, t, u, v, z BROOME 409 v BROOME 479 d BROOME 480 e, k, u BROOME 481 a, b, c, o, qSurrendered Total:16 BL.REGISTERED:15:14:37 12 July 2024

Payments

TypeYearReceipt DateReceipt No.MR LodgedAmountRental AreaEffective DateAmt DueDiscrepancy
Rental202612-May-2025 53539856970$36,848.0047 BL12-Jul-2024 $36,848.00$0.00
Rental202506-May-2024 43405041007$24,885.0063 BL26-Feb-2024 $24,885.00$0.00
Rental202409-May-2023 33461718297$43,616.00116 BL08-May-2018 $43,616.00$0.00
Rental202324-May-2022 23863823767$30,392.00116 BL08-May-2018 $30,392.00$0.00
Rental202206-May-2021 13380426096$27,608.00116 BL08-May-2018 $27,608.00$0.00
Rental202125-May-2020 53921715962$16,008.00116 BL08-May-2018 $16,008.00$0.00
Rental202010-May-2019 10096035$15,776.00116 BL08-May-2018 $15,776.00$0.00
Rental201903-Jan-2018 80055927462$15,544.00116 BL08-May-2018 $15,544.00$0.00

Expenditure

YearForm 5 TypeMin ExpdExp Lodged DateTotal ExpdExemp NoExemp LodgedExemp AmtExemp StatusOutcome DateExploration ActivitiesMining ActivitiesAboriginal SurveyRentAdministrationProspectingStrike Through
2026$141,000.00false
2025$102,000.00false
2024$168,834.0005-Jul-2024 $194,679.00$124,954.00$0.00$18,712.00$46,289.00$4,724.00$0.00false
2023$174,000.0030-Jun-2023 $483,000.00$368,793.00$0.00$0.00$33,707.00$80,500.00$0.00false
2022$174,000.0030-Jun-2022 $669,208.00$615,909.00$0.00$0.00$30,540.00$22,759.00$0.00false
2021$116,000.0030-Jun-2021 $200,334.00$126,193.00$0.00$52,682.00$20,744.00$715.00$0.00false
2020$116,000.0006-Jul-2020 $712,508.00$555,254.00$0.00$25,470.00$31,784.00$100,000.00$0.00false
2019$116,000.0003-Jul-2019 $124,021.00$74,853.00$0.00$0.00$25,968.00$23,200.00$0.00false

Native Title Referrals

Referred to Native Title DateReferral TypeCurrent StatusProcedureDetailsObjectionsWater CommentsDetermination AreasClaimsRepresentative Area Bodies
Tenement ApplicationNative Title is Extinguished - Freehold Land