1 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any exploration activities on Meda Location 15 (Yampi Defence Area CHL/105418). | 08-May-2018 | 03-Sep-2019 |
| 1 | Consent to explore on Meda Location 15 (Yampi Defence Training Area) granted subject to: | 03-Sep-2019 | |
2 | 1 | The Australian Government not guaranteeing access to the Commonwealth Land. | 03-Sep-2019 | |
3 | 1 | The licensee obtaining the relevant approvals required under the Land Acquisitions Act 1989 (Cth). | 03-Sep-2019 | |
4 | 1 | If deed of access is granted, exploration activities being limited to those specified in the deed. | 03-Sep-2019 | |
5 | 1 | Any proposed future mining activities, being subject to separate approval required under the Lands Acquisition Act 1989 (Cth). | 03-Sep-2019 | |
6 | 2 | Exploration and prospecting disturbances, excluding supporting infrastructure, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 12 months after completion of the activity unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 09-Jun-2025 | |
6 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety. | 03-Sep-2019 | 08-Jun-2025 |
7 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 03-Sep-2019 | |
8 | 1 | Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 03-Sep-2019 | |
9 | 2 | The construction and operation of the project and measures to protect the environment to be carried out in accordance with the document titled:
- (PoW Reg ID 80671) "Dreadnought Resources Environmental Management Plan Tarraji-Yampi Project" Version 1.3, dated 2 August 2019 signed by P Chapman, and retained on Department of Mines, Industry Regulation and Safety File No. EARS-POW-80671 as Doc ID 6841916;
- (Pow Reg ID 87726) "Dreadnought Resources Environmental Management Plan Tarraji-Yampi Project Version 1.4" dated 10 August 2020 submitted by Dean Tuck, and retained on Department of Mines, Industry Regulation and Safety File No. EARS-POW-87726 as Doc ID 7613427
| 27-Aug-2020 | |
9 | 1 | The construction and operation of the project and measures to protect the environment to be carried out in accordance with the document titled:
- (PoW Reg ID 80671) "Dreadnought Resources Environmental Management Plan Tarraji-Yampi Project" Version 1.3, dated 2 August 2019 signed by P Chapman, and retained on Department of Mines, Industry Regulation and Safety File No. EARS-POW-80671 as Doc ID 6841916
| 02-Oct-2019 | 26-Aug-2020 |
10 | 1 | All supporting infrastructure for exploration and prospecting including core yards, laydowns, camps, and access tracks (excluding drill lines), being rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Rehabilitation being required by the earlier of 12 months from the infrastructure being no longer required to support exploration, or 12 months from the relevant programme of work expiring, unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 09-Jun-2025 | |
11 | 1 | The tenement holder must maintain appropriate records of exploration/prospecting activities, and associated rehabilitation undertaken, in order to demonstrate compliance with all conditions and environmental management and rehabilitation practice commitments. These records to be made available to the Department upon request. | 09-Jun-2025 | |
12 | 1 | All exploration and prospecting operations to comply with the environmental management and rehabilitation practice commitments provided in the approved programme of work. | 09-Jun-2025 | |
Cond # | Ver | Text | Start | End |
1 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any exploration activities on Meda Location 15 (Yampi Defence Area CHL/105418). | 08-May-2018 | 03-Sep-2019 |
| 1 | Consent to explore on Meda Location 15 (Yampi Defence Training Area) granted subject to: | 03-Sep-2019 | |
2 | 1 | The Australian Government not guaranteeing access to the Commonwealth Land. | 03-Sep-2019 | |
3 | 1 | The licensee obtaining the relevant approvals required under the Land Acquisitions Act 1989 (Cth). | 03-Sep-2019 | |
4 | 1 | If deed of access is granted, exploration activities being limited to those specified in the deed. | 03-Sep-2019 | |
5 | 1 | Any proposed future mining activities, being subject to separate approval required under the Lands Acquisition Act 1989 (Cth). | 03-Sep-2019 | |
6 | 2 | Exploration and prospecting disturbances, excluding supporting infrastructure, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 12 months after completion of the activity unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 09-Jun-2025 | |
6 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety. | 03-Sep-2019 | 08-Jun-2025 |
7 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 03-Sep-2019 | |
8 | 1 | Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 03-Sep-2019 | |
9 | 2 | The construction and operation of the project and measures to protect the environment to be carried out in accordance with the document titled:
- (PoW Reg ID 80671) "Dreadnought Resources Environmental Management Plan Tarraji-Yampi Project" Version 1.3, dated 2 August 2019 signed by P Chapman, and retained on Department of Mines, Industry Regulation and Safety File No. EARS-POW-80671 as Doc ID 6841916;
- (Pow Reg ID 87726) "Dreadnought Resources Environmental Management Plan Tarraji-Yampi Project Version 1.4" dated 10 August 2020 submitted by Dean Tuck, and retained on Department of Mines, Industry Regulation and Safety File No. EARS-POW-87726 as Doc ID 7613427
| 27-Aug-2020 | |
9 | 1 | The construction and operation of the project and measures to protect the environment to be carried out in accordance with the document titled:
- (PoW Reg ID 80671) "Dreadnought Resources Environmental Management Plan Tarraji-Yampi Project" Version 1.3, dated 2 August 2019 signed by P Chapman, and retained on Department of Mines, Industry Regulation and Safety File No. EARS-POW-80671 as Doc ID 6841916
| 02-Oct-2019 | 26-Aug-2020 |
10 | 1 | All supporting infrastructure for exploration and prospecting including core yards, laydowns, camps, and access tracks (excluding drill lines), being rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Rehabilitation being required by the earlier of 12 months from the infrastructure being no longer required to support exploration, or 12 months from the relevant programme of work expiring, unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 09-Jun-2025 | |
11 | 1 | The tenement holder must maintain appropriate records of exploration/prospecting activities, and associated rehabilitation undertaken, in order to demonstrate compliance with all conditions and environmental management and rehabilitation practice commitments. These records to be made available to the Department upon request. | 09-Jun-2025 | |
12 | 1 | All exploration and prospecting operations to comply with the environmental management and rehabilitation practice commitments provided in the approved programme of work. | 09-Jun-2025 | |
Type | Number | Details |
Application to Amend | 569871 | Lodged:14:25:47 08 January 2020Amending:Address (Including DTC Details)From:Principal Place of Business : IRONRINGER (TARRAJI) PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947, xxxxxxxxx@austwidemining.com.au, xxxxxxx400 and DTC :IRONRINGER (TARRAJI) PTY LTD, AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947, xxxxxxxxx@austwidemining.com.au, xxxxxxx400To:Principal Place of Business : IRONRINGER (TARRAJI) PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxxxx997 and DTC :IRONRINGER (TARRAJI) PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxxxx997RECORDED:14:25:47 08 January 2020 |
Application to Amend | 570552 | Lodged:16:08:51 20 January 2020Amending:NameFrom:IRONRINGER (TARRAJI) PTY LTDTo:DREADNOUGHT (KIMBERLEY) PTY LTDRECORDED:16:08:51 20 January 2020 |
Application to Amend | 619331 | Lodged:15:13:10 31 March 2021Amending:NameFrom:DREADNOUGHT (KIMBERLEY) PTY LTDTo:DREADNOUGHT EXPLORATION PTY LTDRECORDED:15:13:10 31 March 2021 |
Application to Amend | 621259 | Lodged:16:26:18 27 April 2021Amending:Address (Including DTC Details)From:DREADNOUGHT EXPLORATION PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxxxx997To:DREADNOUGHT EXPLORATION PTY LTD, MCMAHON MINING TITLE SERVICES PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxxxx997RECORDED:16:26:18 27 April 2021 |
Application to Amend | 674467 | Lodged:13:34:44 27 April 2023Amending:Address (Including DTC Details)From:DREADNOUGHT EXPLORATION PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxxxx997To:DREADNOUGHT EXPLORATION PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 6301, EAST PERTH, WA, 6892, xxxx@mmts.net.au, xxxxxxxxxxx997RECORDED:13:34:44 27 April 2023 |
Extension / Renewal of Term | 674658 | Lodged:09:31:15 01 May 2023Applied For Period:5 YearsRECORDED:09:31:15 01 May 2023GRANTED:10 August 2023Granted Period:5 YearsTerm Extended To:07/05/2028 |
Partial Surrender - Voluntary | 682519 | Lodged:13:29:36 31 July 2023Surrendered Blocks:BROOME 408 l, m, n, q, r, s, w, x
BROOME 409 l, r, s, y, z
BROOME 410 v, w
BROOME 479 c, h, j, n, o
BROOME 480 c, j, w
BROOME 481 p, u, z
BROOME 482 b, l, m, q, r, v, w
BROOME 553 b, j, o, p
BROOME 554 a, bSurrendered Total:39 BL.REGISTERED:13:29:36 31 July 2023 |
Partial Surrender - Voluntary | 697385 | Lodged:15:07:24 26 February 2024Surrendered Blocks:BROOME 408 y
BROOME 409 q, w, x
BROOME 480 d, p
BROOME 481 d, e, j, k, v
BROOME 482 a, f, gSurrendered Total:14 BL.REGISTERED:15:07:24 26 February 2024 |
Partial Surrender - Voluntary | 709334 | Lodged:15:14:37 12 July 2024Surrendered Blocks:BROOME 408 o, p, t, u, v, z
BROOME 409 v
BROOME 479 d
BROOME 480 e, k, u
BROOME 481 a, b, c, o, qSurrendered Total:16 BL.REGISTERED:15:14:37 12 July 2024 |