1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 12-Mar-2014 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 12-Mar-2014 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 12-Mar-2014 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 12-Mar-2014 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 12-Mar-2014 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 12-Mar-2014 | |
7 | 1 | In respect of the area covered by the licence the licensee, if so requested in writing by the Bunuba No 2 the applicants in Federal Court application No. WAD94/12 (WC12/4) , such request being sent by pre-paid post to reach the licensee's address not more than ninety days after the grant of this licence, shall within thirty days of the request execute in favour of the Bunuba No 2 the Regional Standard Heritage Agreement ("RHSA") endorsed by peak industry groups (e.g. the Goldfields/South West/Ngaanyatjarra/Pilbara/Yamatji Land and Sea Council) and offered by the KImberley Land Council.
| 12-Mar-2014 | |
8 | 1 | In respect of the area covered by the licence the licensee, if so requested in writing by the Bunuba Dawangarri Aboriginal Corporation, the native title prescribed body corporate holding the determined native title of the Bunuba People recognised in the Federal Court application No. WAD6133/98 (WC99/19), such request being sent by pre-paid post to reach the licensee's address not more than ninety days after the grant of this licence,shall within thirty days of the request execute in favour of the Bunuba Dawangarri Aboriginal Corporation the Regional Standard Heritage Agreement ("RSHA") endorsed by peak industry groups (e.g. the Goldfields/South West/Ngaayatjarra/Pilbara/Yamatji Land and Sea Council RSHA) and offered by the Kimberley Land Council.
| 12-Mar-2014 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 12-Mar-2014 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 12-Mar-2014 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 12-Mar-2014 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 12-Mar-2014 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 12-Mar-2014 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 12-Mar-2014 | |
7 | 1 | In respect of the area covered by the licence the licensee, if so requested in writing by the Bunuba No 2 the applicants in Federal Court application No. WAD94/12 (WC12/4) , such request being sent by pre-paid post to reach the licensee's address not more than ninety days after the grant of this licence, shall within thirty days of the request execute in favour of the Bunuba No 2 the Regional Standard Heritage Agreement ("RHSA") endorsed by peak industry groups (e.g. the Goldfields/South West/Ngaanyatjarra/Pilbara/Yamatji Land and Sea Council) and offered by the KImberley Land Council.
| 12-Mar-2014 | |
8 | 1 | In respect of the area covered by the licence the licensee, if so requested in writing by the Bunuba Dawangarri Aboriginal Corporation, the native title prescribed body corporate holding the determined native title of the Bunuba People recognised in the Federal Court application No. WAD6133/98 (WC99/19), such request being sent by pre-paid post to reach the licensee's address not more than ninety days after the grant of this licence,shall within thirty days of the request execute in favour of the Bunuba Dawangarri Aboriginal Corporation the Regional Standard Heritage Agreement ("RSHA") endorsed by peak industry groups (e.g. the Goldfields/South West/Ngaayatjarra/Pilbara/Yamatji Land and Sea Council RSHA) and offered by the Kimberley Land Council.
| 12-Mar-2014 | |
Type | Number | Details |
Application to Amend | 430059 | Lodged:14:19:31 28 August 2013Amending:AddressFrom:LEOPOLD DIAMOND COMPANY PTY LTD, UNIT 8, GROUND FLOOR 24 PARKLAND ROAD, OSBORNE PARK, WA, 6017To:LEOPOLD DIAMOND COMPANY PTY LTD, 20 LACEY STREET, BECKENHAM, WA, 6107RECORDED:14:19:31 28 August 2013 |
Application to Amend | 485460 | Lodged:12:10 21 April 2016Amending:AddressFrom:Residential : LEOPOLD DIAMOND COMPANY PTY LTD, 20 LACEY STREET, BECKENHAM, WA, 6107 and Correspondence :LEOPOLD DIAMOND COMPANY PTY LTD, 20 LACEY STREET, BECKENHAM, WA, 6107To:Residential : LEOPOLD DIAMOND COMPANY PTY LTD, SAME AS CORRESPONDENCE and Correspondence :LEOPOLD DIAMOND COMPANY PTY LTD, 82 CLEMENT STREET, SWANBOURNE, WA, 6010RECORDED:12:10 21 April 2016 |
Caveat | 511629 | Lodged:16:00:07 31 July 2017Caveat Type:Consent CaveatCaveator:BROOKING DIAMONDS PTY LTDShares Caveated:80/100 shares LEOPOLD DIAMOND COMPANY PTY LTDRECORDED:16:00:07 31 July 2017WITHDRAWN:08:40 01 February 2018 |
Withdrawal of Dealing | 522540 | Lodged:08:40 01 February 2018In respect to:Caveat 511629RECORDED:08:40 01 February 2018 |
Application to Amend | 522543 | Lodged:08:40 01 February 2018Amending:Address (Including DTC Details)From:Principal Place of Business : BROOKING DIAMONDS PTY LTD, C/- LUCAPA DIAMOND COMPANY LIMITED, PO BOX 298, WEST PERTH, WA, 6872 and DTC :BROOKING DIAMONDS PTY LTD, C/- LUCAPA DIAMOND COMPANY LIMITED, PO BOX 298, WEST PERTH, WA, 6872To:Principal Place of Business : BROOKING DIAMONDS PTY LTD, PO BOX 1091, WEST PERTH, WA, 6872 and DTC :BROOKING DIAMONDS PTY LTD, PO BOX 1091, WEST PERTH, WA, 6872RECORDED:08:40 01 February 2018 |
Excess Tonnage | 528215 | Lodged:15:04:37 17 April 2018RECORDED:15:04:37 17 April 2018GRANTED:15:10:42 08 May 2018Approved for an additional 2,500 tonnes |
Extension / Renewal of Term | 548992 | Lodged:13:58:04 08 March 2019Applied For Period:5 YearsRECORDED:13:58:04 08 March 2019GRANTED:16 April 2019Granted Period:5 YearsTerm Extended To:11/03/2024 |
Extension / Renewal of Term | 698138 | Lodged:10:03:45 07 March 2024Applied For Period:2 YearsRECORDED:10:03:45 07 March 2024GRANTED:13 May 2024Granted Period:2 YearsTerm Extended To:11/03/2026 |