Extracted from MTO on 04-Jul-2025 00:38,
last changed 04-Jul-2025.
# | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 11-Nov-2015 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 11-Nov-2015 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 11-Nov-2015 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 11-Nov-2015 | |
5 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any exploration activities on the foreshore, seabed and navigable waters. | 11-Nov-2015 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 11-Nov-2015 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 11-Nov-2015 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 11-Nov-2015 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 11-Nov-2015 | |
5 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any exploration activities on the foreshore, seabed and navigable waters. | 11-Nov-2015 | |
Type | Number | Details |
Application to Amend | 432191 | Lodged:10:54:12 01 October 2013Amending:AddressFrom:MOBILE CONCRETING SOLUTIONS PTY LTD, M & M WALTER CONSULTING, PO BOX 8197, SUBIACO EAST, WA, 6008To:MOBILE CONCRETING SOLUTIONS PTY LTD, C/- M & M WALTER CONSULTING, PO BOX 8197, SUBIACO EAST, WA, 6008RECORDED:10:54:12 01 October 2013 |
Expiry - Full | 590462 | EFFECTIVE:Midnight 10 November 2020 |