Extracted from MTO on 08-Jul-2025 01:52,
last changed 26-Jun-2025.
# | Ver | Text | Start | End |
1 | 1 | All exploration activities are to be made safe immediately after completion. | 08-Jun-2023 | |
2 | 1 | All waste materials, rubbish, plastic sample bags and abandoned equipment being removed from the mining tenement prior to or at the termination of exploration program. | 08-Jun-2023 | |
3 | 1 | All exploration activities must be rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety (DMIRS). Rehabilitation being required no later than 6 months after the activity is cinducted unless otherwise approved in writing by the Environmental Officer, DMIRS. | 08-Jun-2023 | |
| 1 | Consent to explore on Yampi Port Area Reserve 50387 and the Foreshore, Seabed and Navigable Water given subject to the following conditions: | 08-Jun-2023 | |
4 | 1 | At least five working days prior to accessing the port reserve, the licensee providing the Harbour Master, Kimberley Port Authority with an itinerary and program of the locations of operations on the licence area and informing at least five days in advance of any changes to that itinerary. | 08-Jun-2023 | |
5 | 1 | Unless the prior written approval of the Executive Director, Resource and Environmental Compliance, DMIRS is first obtained exploration operations within the licence area being restricted to the following activities:
- reconnaissance by aircraft, helicopter, hovercraft, boat and amphibious vehicle;
- bathymetric sounding and side scan sonar profiling, airborne radiometric and magnetic surveys, sea floor mapping, imagery and photography;
- seismic survey (non-explosive) subject to whale, turtle watch and fishery protection procedures prescribed by the Department of Biodiversity Conservation and Attractions (DBCA) and the Department of Primary Industries and Regional Development.
| 08-Jun-2023 | |
6 | 1 | Prior to any activity involving environmental disturbance to the seabed and general marine environment including:
- vibro and shallow coring
- drilling
- sampling (grab, siphoning, etc.)
- dredging
the licensee providing an exploration and environmental management program for written approval of the Executive Director, Resource and Environmental Compliance, DMIRS in consultation with the Department of Biodiversity Conservation and Attractions (DBCA). | 08-Jun-2023 | |
7 | 1 | The licensee not establishing any camping facilities, access tracks, boat moorings, fuel depots or similar establishments on any coastal mangrove areas or beach/foreshore environments without the prior written approval of the Executive Director, Resource and Environmental Compliance, DMIRS in consultation with the Regional Manager, DBCA. | 08-Jun-2023 | |
8 | 1 | No dumping of rubbish, discharge of fuel, oil or other pollutants into the marine environment. | 08-Jun-2023 | |
9 | 1 | Damage to coral reefs, seagrass meadows and mangroves being avoided. | 08-Jun-2023 | |
10 | 1 | Turtle and bird nesting areas not being disturbed. | 08-Jun-2023 | |
11 | 1 | Only low toxicity drilling muds or additives being used in offshore drilling operations. | 08-Jun-2023 | |
12 | 1 | No explosives being used in exploration without the prior written approval of the Executive Director, Resource and Environmental Compliance, DMIRS. | 08-Jun-2023 | |
13 | 1 | If in the opinion of the Executive Director, Resource and Environmental Compliance, DMIRS the exploration operations are causing any damage to or undue interference with living marine resources or their environment on any part or parts of the licence area, the licensee ceasing exploration on such part or parts within 24 hours of notification from the Executive Director, Resource and Environmental Compliance, DMIRS. | 08-Jun-2023 | |
14 | 1 | The licensee carrying out exploration activities in such a manner as not to damage any pipeline, wellhead, capped well or other equipment associated with seabed exploration and mining. | 08-Jun-2023 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All exploration activities are to be made safe immediately after completion. | 08-Jun-2023 | |
2 | 1 | All waste materials, rubbish, plastic sample bags and abandoned equipment being removed from the mining tenement prior to or at the termination of exploration program. | 08-Jun-2023 | |
3 | 1 | All exploration activities must be rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety (DMIRS). Rehabilitation being required no later than 6 months after the activity is cinducted unless otherwise approved in writing by the Environmental Officer, DMIRS. | 08-Jun-2023 | |
| 1 | Consent to explore on Yampi Port Area Reserve 50387 and the Foreshore, Seabed and Navigable Water given subject to the following conditions: | 08-Jun-2023 | |
4 | 1 | At least five working days prior to accessing the port reserve, the licensee providing the Harbour Master, Kimberley Port Authority with an itinerary and program of the locations of operations on the licence area and informing at least five days in advance of any changes to that itinerary. | 08-Jun-2023 | |
5 | 1 | Unless the prior written approval of the Executive Director, Resource and Environmental Compliance, DMIRS is first obtained exploration operations within the licence area being restricted to the following activities:
- reconnaissance by aircraft, helicopter, hovercraft, boat and amphibious vehicle;
- bathymetric sounding and side scan sonar profiling, airborne radiometric and magnetic surveys, sea floor mapping, imagery and photography;
- seismic survey (non-explosive) subject to whale, turtle watch and fishery protection procedures prescribed by the Department of Biodiversity Conservation and Attractions (DBCA) and the Department of Primary Industries and Regional Development.
| 08-Jun-2023 | |
6 | 1 | Prior to any activity involving environmental disturbance to the seabed and general marine environment including:
- vibro and shallow coring
- drilling
- sampling (grab, siphoning, etc.)
- dredging
the licensee providing an exploration and environmental management program for written approval of the Executive Director, Resource and Environmental Compliance, DMIRS in consultation with the Department of Biodiversity Conservation and Attractions (DBCA). | 08-Jun-2023 | |
7 | 1 | The licensee not establishing any camping facilities, access tracks, boat moorings, fuel depots or similar establishments on any coastal mangrove areas or beach/foreshore environments without the prior written approval of the Executive Director, Resource and Environmental Compliance, DMIRS in consultation with the Regional Manager, DBCA. | 08-Jun-2023 | |
8 | 1 | No dumping of rubbish, discharge of fuel, oil or other pollutants into the marine environment. | 08-Jun-2023 | |
9 | 1 | Damage to coral reefs, seagrass meadows and mangroves being avoided. | 08-Jun-2023 | |
10 | 1 | Turtle and bird nesting areas not being disturbed. | 08-Jun-2023 | |
11 | 1 | Only low toxicity drilling muds or additives being used in offshore drilling operations. | 08-Jun-2023 | |
12 | 1 | No explosives being used in exploration without the prior written approval of the Executive Director, Resource and Environmental Compliance, DMIRS. | 08-Jun-2023 | |
13 | 1 | If in the opinion of the Executive Director, Resource and Environmental Compliance, DMIRS the exploration operations are causing any damage to or undue interference with living marine resources or their environment on any part or parts of the licence area, the licensee ceasing exploration on such part or parts within 24 hours of notification from the Executive Director, Resource and Environmental Compliance, DMIRS. | 08-Jun-2023 | |
14 | 1 | The licensee carrying out exploration activities in such a manner as not to damage any pipeline, wellhead, capped well or other equipment associated with seabed exploration and mining. | 08-Jun-2023 | |
Type | Number | Details |
Iron Ore Inclusion | 400227 | Lodged:09:56:20 25 June 2012RECORDED:09:56:21 25 June 2012 |
Application to Amend | 430666 | Lodged:11:00 05 September 2013Amending:AddressFrom:PLUTON RESOURCES LIMITED, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947To:PLUTON RESOURCES LIMITED, PO BOX 1622, WEST PERTH, WA, 6872RECORDED:11:00 05 September 2013 |
Application to Amend | 471153 | Lodged:09:30 14 July 2015Amending:AddressFrom:PLUTON RESOURCES LIMITED, PO BOX 1622, WEST PERTH, WA, 6872To:PLUTON RESOURCES LIMITED, SUITE 8, LEVEL 1, 12-20 RAILWAY ROAD, SUBIACO, WA, 6008RECORDED:09:30 14 July 2015 |
Application to Amend | 472798 | Lodged:13:57:07 13 August 2015Amending:AddressFrom:PLUTON RESOURCES LIMITED, SUITE 8, LEVEL 1, 12-20 RAILWAY ROAD, SUBIACO, WA, 6008To:PLUTON RESOURCES LIMITED, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849RECORDED:13:57:07 13 August 2015 |
Application to Amend | 490190 | Lodged:12:39:57 07 July 2016Amending:Address (Including DTC Details)From:PLUTON RESOURCES LIMITED, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849To:PLUTON RESOURCES LIMITED, HETHERINGTON EXPLORATION & MINING TITLE SERVICES (WA) PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxx977RECORDED:12:39:57 07 July 2016 |
Application to Amend | 589916 | Lodged:11:11:08 10 November 2020Amending:Address (Including DTC Details)From:Principal Place of Business : PLUTON RESOURCES LIMITED, SAME AS CORRESPONDENCE and DTC :PLUTON RESOURCES LIMITED, HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxx977To:Principal Place of Business : PLUTON RESOURCES LIMITED, C/- HG TITLE SERVICES PTY LTD, PO BOX Z5312 ST GEORGES TERRACE, PERTH, WA, 6831, xxxxxxxxxxxxxx@hopgoodganim.com.au, xxxxx163 and DTC :PLUTON RESOURCES LIMITED, SENIOR TENEMENT MANAGER, C/- HG TITLE SERVICES PTY LTD, PO BOX Z5312 ST GEORGES TERRACE, PERTH, WA, 6831, xxxxxxxxxxxxxx@hopgoodganim.com.au, xxxxx163RECORDED:11:11:08 10 November 2020 |
Application to Amend | 590209 | Lodged:14:30 11 November 2020REJECTED:14:30 11 November 2020 |