Extracted from MTO on 09-Aug-2022 05:07,
last changed 29-Jun-2022.
# | Ver | Text | Start | End |
1 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 24-Apr-2017 | |
2 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 24-Apr-2017 | |
3 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 24-Apr-2017 | |
4 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 24-Apr-2017 | |
5 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 24-Apr-2017 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 24-Apr-2017 | |
2 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 24-Apr-2017 | |
3 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 24-Apr-2017 | |
4 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 24-Apr-2017 | |
5 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 24-Apr-2017 | |
Type | Number | Details |
Extension of Time | 496041 | Lodged:10:05:20 17 October 2016Type:SecurityRECORDED:10:05:20 17 October 2016APPROVED:15:30 26 October 2016Application to extend time up to the close of business on 17/10/2016. |
Application to Amend | 496038 | Lodged:10:05:26 17 October 2016Amending:LocalityFrom:CoolgardieTo:Taurus DamRECORDED:10:05:26 17 October 2016 |
Application to Amend | 534349 | Lodged:10:16:01 05 July 2018Amending:Address (Including DTC Details)From:Principal Place of Business : HURRICANE PROSPECTING PTY LTD, 61 THE STRAND, BAYSWATER, WA, 6053, xxxxxxxxxxxx@gmail.com, xxxxxxx404 and DTC :HURRICANE PROSPECTING PTY LTD, 61 THE STRAND, BAYSWATER, WA, 6053To:Principal Place of Business : HURRICANE PROSPECTING PTY LTD, DEBLIN TENEMENT MANAGEMENT SERVICES, PO BOX 456, MOUNT HAWTHORN, WA, 6915, xxxx@deblin.com.au, xxxxxxx190 and DTC :HURRICANE PROSPECTING PTY LTD, THE TENEMENT MANAGER, DEBLIN TENEMENT MANAGEMENT SERVICES, PO BOX 456, MOUNT HAWTHORN, WA, 6915, xxxx@deblin.com.au, xxxxxxx190RECORDED:10:16:01 05 July 2018 |
Forfeiture | 560733 | Initiated:15/08/2019 for non-compliance with reporting requirementsRECORDED:08:30 15 August 2019Notice Issued:Regulation 50 Notice sent 15/08/2019 for non-compliance with reporting requirements pursuant to Sec 115A.Compliance Date:19/09/2019FINALISED:Order by Minister on 28 May 2020 that E 25/552 be Penalty Imposed |
Fine | 578956 | Fine in respect to:Forfeiture Process 560733Fine reason:Non-compliance with mineral exploration reporting provisionsPenalty amount:$450.00Notification date:03/06/2020Due date:08/07/2020Pursuant to:Section 96A(5)RECORDED:29 May 2020PAYMENT RECEIVED:08 June 2020FINALISED:08 June 2020Receipt Number:54297817912Amount:$450.00Remaining balance:$0.00 |
Extension of Time | 626800 | Lodged:15:14:39 23 June 2021Type:Form 5RECORDED:15:14:39 23 June 2021APPROVED:11:33:45 24 June 2021Time to lodge extended to 30 June 2021 |
Extension / Renewal of Term | 647640 | Lodged:08:30 22 April 2022Applied For Period:5 YearsRECORDED:08:30 22 April 2022 |
Extension of Time | 648311 | Lodged:16:07:40 02 May 2022Type:OtherRECORDED:16:07:40 02 May 2022APPROVED:10:21:21 03 May 2022Time to lodge extended to COB 6th June 2022 |