| 1 | In respect to the area designated as CPL 21 in TENGRAPH the following conditions apply: | 08-Aug-2017 | |
1 | 1 | Prior to any ground-disturbing activity, as defined by the Executive Director, Environment Division, DMIRS the licensee preparing a detailed program for each phase of proposed exploration for approval of the Executive Director, Environment Division, DMIRS. The program to include:
- maps and/or aerial photographs showing all proposed routes, construction and upgrading of tracks, camps, drill sites and any other disturbances;
- the purpose, specifications and life of all proposed disturbances;
- proposals which may disturb any declared rare or geographically restricted flora and fauna; and
- techniques, prescriptions and timetable for the rehabilitation of all proposed disturbances
| 08-Aug-2017 | |
2 | 1 | The licensee, at his expense, rehabilitating all areas cleared, explored or otherwise disturbed during the term of the licence to the satisfaction of the Executive Director, Environment Division, DMIRS. Such rehabilitation as is appropriate and may include:
- stockpiling and return of topsoil;
- backfilling all holes, trenches and costeans;
- ripping;
- contouring to the original landform;
- revegetation with seed; and
- capping and backfilling of all drill holes.
| 08-Aug-2017 | |
3 | 1 | Prior to the cessation of exploration/prospecting activity the licensee notifying the Environmental Officer, DMIRS and arranging an inspection as required. | 08-Aug-2017 | |
4 | 1 | The rights of ingress to and egress from Miscellaneous Licence 24/85 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 08-Aug-2017 | |
5 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, DMIRS. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMIRS. | 08-Aug-2017 | |
6 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 08-Aug-2017 | |
7 | 1 | Unless the written approval of the Environmental Officer, DMIRS is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 08-Aug-2017 | |
8 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 08-Aug-2017 | |
9 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 08-Aug-2017 | |
Cond # | Ver | Text | Start | End |
| 1 | In respect to the area designated as CPL 21 in TENGRAPH the following conditions apply: | 08-Aug-2017 | |
1 | 1 | Prior to any ground-disturbing activity, as defined by the Executive Director, Environment Division, DMIRS the licensee preparing a detailed program for each phase of proposed exploration for approval of the Executive Director, Environment Division, DMIRS. The program to include:
- maps and/or aerial photographs showing all proposed routes, construction and upgrading of tracks, camps, drill sites and any other disturbances;
- the purpose, specifications and life of all proposed disturbances;
- proposals which may disturb any declared rare or geographically restricted flora and fauna; and
- techniques, prescriptions and timetable for the rehabilitation of all proposed disturbances
| 08-Aug-2017 | |
2 | 1 | The licensee, at his expense, rehabilitating all areas cleared, explored or otherwise disturbed during the term of the licence to the satisfaction of the Executive Director, Environment Division, DMIRS. Such rehabilitation as is appropriate and may include:
- stockpiling and return of topsoil;
- backfilling all holes, trenches and costeans;
- ripping;
- contouring to the original landform;
- revegetation with seed; and
- capping and backfilling of all drill holes.
| 08-Aug-2017 | |
3 | 1 | Prior to the cessation of exploration/prospecting activity the licensee notifying the Environmental Officer, DMIRS and arranging an inspection as required. | 08-Aug-2017 | |
4 | 1 | The rights of ingress to and egress from Miscellaneous Licence 24/85 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 08-Aug-2017 | |
5 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, DMIRS. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMIRS. | 08-Aug-2017 | |
6 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 08-Aug-2017 | |
7 | 1 | Unless the written approval of the Environmental Officer, DMIRS is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 08-Aug-2017 | |
8 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 08-Aug-2017 | |
9 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 08-Aug-2017 | |
Type | Number | Details |
Objection | 476047 | Lodged:15:43:03 16 October 2015Objectors:SIBERIA MINING CORPORATION PTY LTDObjection Type:Tenement ApplicationRECORDED:15:43:03 16 October 2015FINALISED:15:00 07 February 2017Wardens Decision Made on:15:07:38 07 February 2017Wardens Decision Status:DismissedWardens Decision Text:Objection 476047 Dismissed signed off by Warden Maughan |
Application to Amend | 500020 | Lodged:15:40 19 January 2017Amending:Address (Including DTC Details)From:Principal Place of Business : ATRIPLEX PTY LIMITED, LEVEL 1, 37 ORD STREET, WEST PERTH, WA, 6005 and DTC :ATRIPLEX PTY LIMITED, PO BOX 1380, WEST PERTH, WA, 6872To:Principal Place of Business : ATRIPLEX PTY LIMITED, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931 and DTC :ATRIPLEX PTY LIMITED, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931RECORDED:15:40 19 January 2017 |
Forfeiture | 540665 | Initiated:17/10/2018 for non-compliance with rent requirementsRECORDED:14:35:52 16 October 2018Notice Issued:Regulation 50 Notice sent 17/10/2018 for non-compliance with rent requirements pursuant to Reg 109/Sec 63A- non payment of rent.Compliance Date:21/11/2018FINALISED:Order by Minister on 11 December 2018 that E 24/203 be Penalty Imposed |
Application to Amend | 542367 | Lodged:14:40 08 November 2018Amending:Address (Including DTC Details)From:Principal Place of Business : ATRIPLEX PTY LIMITED, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931 and DTC :ATRIPLEX PTY LIMITED, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931To:Principal Place of Business : ATRIPLEX PTY LIMITED, C/-EASTERN GOLDFIELDS LTD, LEVEL 2, 220 ST GEORGES TERRACE, PERTH, WA, 6000 and DTC :ATRIPLEX PTY LIMITED, JACQUILINE LY, C/-EASTERN GOLDFIELDS LTD, PO BOX 7207, COLISTER'S SQUARE, PERTH, WA, 6850RECORDED:14:40 08 November 2018 |
Fine | 544431 | Fine in respect to:Forfeiture Process 540665Fine reason:Non-compliance with rent obligationsPenalty amount:$188.00Notification date:11/12/2018Due date:15/01/2019Pursuant to:Section 96A(5)RECORDED:11 December 2018PAYMENT RECEIVED:21 December 2018FINALISED:03 January 2019Receipt Number:10080891Amount:$188.00Remaining balance:$0.00 |
Application to Amend | 569168 | Lodged:08:30 19 December 2019Amending:Address (Including DTC Details)From:Principal Place of Business : ATRIPLEX PTY LIMITED, C/-EASTERN GOLDFIELDS LTD, LEVEL 2, 220 ST GEORGES TERRACE, PERTH, WA, 6000 and DTC :ATRIPLEX PTY LIMITED, JACQUILINE LY, C/-EASTERN GOLDFIELDS LTD, PO BOX 7207, COLISTER'S SQUARE, PERTH, WA, 6850To:Principal Place of Business : ATRIPLEX PTY LIMITED, C/-ORA BANDA MINING LTD, LEVEL 1, 2 KINGS PARK ROAD, PERTH, WA, 6005 and DTC :ATRIPLEX PTY LIMITED, JACQUILINE LY, C/- ORA BANDA MINING LTD, PO BOX 464, WEST PERTH, WA, 6872, xxxxxxxxx@orabandamining.com.au, xxxxx548RECORDED:08:30 19 December 2019 |
Application to Amend | 569178 | Lodged:08:30 19 December 2019Amending:Address (Including DTC Details)From:Principal Place of Business : ATRIPLEX PTY LIMITED, C/-EASTERN GOLDFIELDS LTD, LEVEL 2, 220 ST GEORGES TERRACE, PERTH, WA, 6000 and DTC :ATRIPLEX PTY LIMITED, JACQUILINE LY, C/-EASTERN GOLDFIELDS LTD, PO BOX 7207, COLISTER'S SQUARE, PERTH, WA, 6850To:Principal Place of Business : ATRIPLEX PTY LIMITED, C/- ORA BANDA MINING LTD, LEVEL 1, 2 KINGS PARK ROAD, WEST PERTH, WA, 6005, xxxxxxxxx@orabandamining.com.au, xxxxx548 and DTC :ATRIPLEX PTY LIMITED, ATRIPLEX PTY LIMITED, C/- ORA BANDA MINING LTD, PO BOX 464, WEST PERTH, WA, 6872, xxxxxxxxx@orabandamining.com.au, xxxxx548RECORDED:08:30 19 December 2019DUPLICATED |
Extension / Renewal of Term | 655197 | Lodged:14:58:18 05 August 2022PENDING |