1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety. | 17-Jul-2020 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 17-Jul-2020 | |
3 | 1 | Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 17-Jul-2020 | |
4 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 17-Jul-2020 | |
5 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 17-Jul-2020 | |
6 | 1 | No mining within 30 metres of either side and to a depth of 15 metres of the Rail Corridor Land 15 (RCL/15 Kalgoorlie West to Mt Walton Road) as shown in TENGRAPH without the prior written approval of the Minister responsible for the Mining Act 1978. | 17-Jul-2020 | |
7 | 1 | No surface excavation approaching closer to the boundary of the Safety Zone established by Condition 6 hereof than a distance equal to three times the depth of the excavation without the prior written approval of Mines Safety, DMIRS. | 17-Jul-2020 | |
8 | 1 | Mining below 15 metres from the natural surface of the land in the Safety Zone established in Condition 6 hereof being approved by Mines Safety, DMIRS in consultation with the operator of the railway on corridor land. | 17-Jul-2020 | |
9 | 1 | No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 6 hereof without the prior approval of the operator of the railway on corridor land. | 17-Jul-2020 | |
10 | 1 | The Licensee not excavating, drilling, installing, erecting, depositing or permitting to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 6 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of Mines Safety, DMIRS. | 17-Jul-2020 | |
11 | 1 | No explosives being used or stored within one hundred and fifty (150) metres of the rail corridor land without the prior written consent of the Director, Dangerous Goods and Petroleum Safety, DMIRS. | 17-Jul-2020 | |
12 | 1 | The rights of ingress to and egress from the rail corridor land being at all times preserved to the employees, contractors and agents of the operator of the railway on corridor land, and the Public Transport Authority of WA. | 17-Jul-2020 | |
13 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the rail corridor land. | 17-Jul-2020 | |
14 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any mining activities on Railway Station Yard Reserve 41924. | 17-Jul-2020 | |
15 | 1 | The rights of ingress to and egress from Miscellaneous Licence 16/103 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 17-Jul-2020 | |
| 1 | In respect to the area designated as CPL 50 (Former Credo Pastoral Lease) in TENGRAPH the following conditions apply: | 17-Jul-2020 | |
16 | 1 | Prior to any ground-disturbing activity, as defined by the Executive Director, Resource and Environmental Compliance, Department of Mines, Industry Regulation and Safety (DMIRS) the licensee preparing a detailed program for each phase of proposed exploration for approval of the Executive Director, Resource and Environmental Compliance, DMIRS. The program to include:
- maps and/or aerial photographs showing all proposed routes, construction and upgrading of tracks, camps, drill sites and any other disturbances;
- the purpose, specifications and life of all proposed disturbances;
- proposals which may disturb any declared rare or geographically restricted flora and fauna; and
- techniques, prescriptions and timetable for the rehabilitation of all proposed disturbances
| 17-Jul-2020 | |
17 | 1 | The licensee, at his expense, rehabilitating all areas cleared, explored or otherwise disturbed during the term of the licence to the satisfaction of the Executive Director, Resource and Environmental Compliance, DMIRS. Such rehabilitation as is appropriate and may include:
- stockpiling and return of topsoil;
- backfilling all holes, trenches and costeans;
- ripping;
- contouring to the original landform;
- revegetation with seed; and
- capping and backfilling of all drill holes.
| 17-Jul-2020 | |
18 | 1 | Prior to the cessation of exploration/prospecting activity the licensee notifying the Environmental Officer, DMIRS and arranging an inspection as required. | 17-Jul-2020 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety. | 17-Jul-2020 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 17-Jul-2020 | |
3 | 1 | Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 17-Jul-2020 | |
4 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 17-Jul-2020 | |
5 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 17-Jul-2020 | |
6 | 1 | No mining within 30 metres of either side and to a depth of 15 metres of the Rail Corridor Land 15 (RCL/15 Kalgoorlie West to Mt Walton Road) as shown in TENGRAPH without the prior written approval of the Minister responsible for the Mining Act 1978. | 17-Jul-2020 | |
7 | 1 | No surface excavation approaching closer to the boundary of the Safety Zone established by Condition 6 hereof than a distance equal to three times the depth of the excavation without the prior written approval of Mines Safety, DMIRS. | 17-Jul-2020 | |
8 | 1 | Mining below 15 metres from the natural surface of the land in the Safety Zone established in Condition 6 hereof being approved by Mines Safety, DMIRS in consultation with the operator of the railway on corridor land. | 17-Jul-2020 | |
9 | 1 | No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 6 hereof without the prior approval of the operator of the railway on corridor land. | 17-Jul-2020 | |
10 | 1 | The Licensee not excavating, drilling, installing, erecting, depositing or permitting to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 6 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of Mines Safety, DMIRS. | 17-Jul-2020 | |
11 | 1 | No explosives being used or stored within one hundred and fifty (150) metres of the rail corridor land without the prior written consent of the Director, Dangerous Goods and Petroleum Safety, DMIRS. | 17-Jul-2020 | |
12 | 1 | The rights of ingress to and egress from the rail corridor land being at all times preserved to the employees, contractors and agents of the operator of the railway on corridor land, and the Public Transport Authority of WA. | 17-Jul-2020 | |
13 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the rail corridor land. | 17-Jul-2020 | |
14 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any mining activities on Railway Station Yard Reserve 41924. | 17-Jul-2020 | |
15 | 1 | The rights of ingress to and egress from Miscellaneous Licence 16/103 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 17-Jul-2020 | |
| 1 | In respect to the area designated as CPL 50 (Former Credo Pastoral Lease) in TENGRAPH the following conditions apply: | 17-Jul-2020 | |
16 | 1 | Prior to any ground-disturbing activity, as defined by the Executive Director, Resource and Environmental Compliance, Department of Mines, Industry Regulation and Safety (DMIRS) the licensee preparing a detailed program for each phase of proposed exploration for approval of the Executive Director, Resource and Environmental Compliance, DMIRS. The program to include:
- maps and/or aerial photographs showing all proposed routes, construction and upgrading of tracks, camps, drill sites and any other disturbances;
- the purpose, specifications and life of all proposed disturbances;
- proposals which may disturb any declared rare or geographically restricted flora and fauna; and
- techniques, prescriptions and timetable for the rehabilitation of all proposed disturbances
| 17-Jul-2020 | |
17 | 1 | The licensee, at his expense, rehabilitating all areas cleared, explored or otherwise disturbed during the term of the licence to the satisfaction of the Executive Director, Resource and Environmental Compliance, DMIRS. Such rehabilitation as is appropriate and may include:
- stockpiling and return of topsoil;
- backfilling all holes, trenches and costeans;
- ripping;
- contouring to the original landform;
- revegetation with seed; and
- capping and backfilling of all drill holes.
| 17-Jul-2020 | |
18 | 1 | Prior to the cessation of exploration/prospecting activity the licensee notifying the Environmental Officer, DMIRS and arranging an inspection as required. | 17-Jul-2020 | |
Type | Number | Details |
Objection | 530946 | Lodged:08:30 23 May 2018Objectors:SIBERIA MINING CORPORATION PTY LTDObjection Type:Tenement ApplicationRECORDED:08:30 23 May 2018FINALISED:16:19:44 27 June 2019Wardens Decision Made on:14:15 27 June 2019Wardens Decision Status:FinalisedWardens Decision Text:Objection withdrawn by consent. |
Application to Amend | 559636 | Lodged:12:59:48 01 August 2019Amending:Address (Including DTC Details)From:Principal Place of Business : BLACK MOUNTAIN GOLD LIMITED, 163-167 STIRLING HIGHWAY, NEDLANDS, WA, 6009 and DTC :BLACK MOUNTAIN GOLD LIMITED, BIANCA TAVEIRA, PO BOX 1104, NEDLANDS, WA, 6909, xxxxxxxxxxxxxx@intermin.com.au, xxxxxxxxx699To:Principal Place of Business : BLACK MOUNTAIN GOLD LIMITED, 163-167 STIRLING HIGHWAY, NEDLANDS, WA, 6009, xxxxxxxxxxxxxx@horizonminerals.com.au, xxxxxxxxx699 and DTC :BLACK MOUNTAIN GOLD LIMITED, BIANCA TAVEIRA, PO BOX 1104, NEDLANDS, WA, 6909, xxxxxxxxxxxxxx@horizonminerals.com.au, xxxxxxxxx699RECORDED:12:59:48 01 August 2019 |