1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, DMIRS. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMIRS. | 27-Mar-2018 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 27-Mar-2018 | |
3 | 1 | Unless the written approval of the Environmental Officer, DMIRS is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 27-Mar-2018 | |
4 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 27-Mar-2018 | |
5 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 27-Mar-2018 | |
6 | 1 | The rights of ingress to and egress from Miscellaneous Licenced 15/224, 15/344 and 16/78 being at all times preserved to the licensee's and no interference with the purpose or installations connected to the licences. | 27-Mar-2018 | |
7 | 1 | No interference with Geodetic Survey Station SSM-KG 18 and SSM-UK 252 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 27-Mar-2018 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, DMIRS. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMIRS. | 27-Mar-2018 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 27-Mar-2018 | |
3 | 1 | Unless the written approval of the Environmental Officer, DMIRS is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 27-Mar-2018 | |
4 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 27-Mar-2018 | |
5 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 27-Mar-2018 | |
6 | 1 | The rights of ingress to and egress from Miscellaneous Licenced 15/224, 15/344 and 16/78 being at all times preserved to the licensee's and no interference with the purpose or installations connected to the licences. | 27-Mar-2018 | |
7 | 1 | No interference with Geodetic Survey Station SSM-KG 18 and SSM-UK 252 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 27-Mar-2018 | |
Type | Number | Details |
Objection | 502041 | Lodged:16:15:50 02 March 2017Objectors:SIBERIA MINING CORPORATION PTY LTDObjection Type:Tenement ApplicationRECORDED:16:15:50 02 March 2017Wardens Decision Made on:11:29 20 April 2017Wardens Decision Status:FinalisedWardens Decision Text:Mining Registrar actioned withdrawal of objections pursuant to sec 59(2) - letter authored by same employee of Eastern Goldfields Ltd whom lodged objection by authorisation of Siberia Mining Corporation Pty Ltd.WITHDRAWN:11:29 20 April 2017 |
Objection | 502061 | Lodged:10:29:41 03 March 2017Objectors:EVOLUTION MINING (PHOENIX) PTY LIMITEDObjection Type:Tenement ApplicationRECORDED:10:29:41 03 March 2017WITHDRAWN:00:00 12 October 2017Wardens Decision Made on:00:00 12 October 2017Wardens Decision Status:FinalisedWardens Decision Text:Objection withdrawn by consent. |
Objection | 502062 | Lodged:10:29:41 03 March 2017Objectors:HAYES MINING PTY LTDObjection Type:Tenement ApplicationRECORDED:10:29:41 03 March 2017WITHDRAWN:00:00 13 October 2017Wardens Decision Made on:00:00 12 October 2017Wardens Decision Status:FinalisedWardens Decision Text:Objection withdrawn by consent |
Application to Amend | 527894 | Lodged:10:15:09 13 April 2018Amending:Address (Including DTC Details)From:Principal Place of Business : BEACON MINING PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, UNIT 28, 168 GUILFORD ROAD, MAYLANDS, WA, 6051 and DTC :BEACON MINING PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, UNIT 28, 168 GUILFORD ROAD, MAYLANDS, WA, 6051To:Principal Place of Business : BEACON MINING PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxxxxxx997 and DTC :BEACON MINING PTY LTD, MCMAHON MINING TITLE SERVICES PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxxxxxx997RECORDED:10:15:09 13 April 2018 |
Partial Surrender - Voluntary | 573649 | Lodged:09:49 09 March 2020Surrendered Blocks:KALGOORLIE 2316 e, k
KALGOORLIE 2317 a, f
KALGOORLIE 2388 d, e, h, j, k, o, p
KALGOORLIE 2389 a, f, g, h, j, k, l, m, n
KALGOORLIE 2390 fSurrendered Total:21 BL.REGISTERED:09:49 09 March 2020 |