Tenement Summary

Identifier:E 15/1531Type:Exploration Licence
Status:LiveDistrict:COOLGARDIE
Lodged:ONLINEArea:3 BL
Purposes:Term:5 Years
Markout:Received:16-Jun-2016 15:38
Commence:15-Feb-2017 Expiry:14-Feb-2022

Holders

Company NameSharesTotal Shares
EVOLUTION MINING (MUNGARI) PTY LTD100100

Applicants on Receival

Company NameSharesTotal Shares
EVOLUTION MINING (MUNGARI) PTY LTD100100

Relationships

Relationship TypeDealingDealing StatusTenementTenement Status
Amalgamation (Same Holder)Amalgamation 501415GrantedP 15/4827Dead
Amalgamation (Same Holder)Amalgamation 501416GrantedP 15/4828Dead

Shires

Shire NameShire NumberStartArea
COOLGARDIE SHIRE196016-Jun-2016 3.00000 BL

Conditions

#VerTextStartEnd
11All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program.15-Feb-2017
21Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations.15-Feb-2017
31The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment.15-Feb-2017
41The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-
  • the grant of the Licence; or
  • registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer.
15-Feb-2017
51No mining within 30 metres of either side and to a depth of 15 metres of the Rail Corridor Land RCL/15 (Kalgoorlie West to Mount Walton Road) as shown in TENGRAPH without the prior written approval of the Minister responsible for the Mining Act 1978.15-Feb-2017
61No surface excavation approaching closer to the boundary of the Safety Zone established by Condition 5  hereof than a distance equal to three times the depth of the excavation without the prior written approval of the State Mining Engineer, DMP.15-Feb-2017
71Mining below 15 metres from the natural surface of the land in the Safety Zone established in Condition 5 hereof being approved by the State Mining Engineer, DMP in consultation with the operator of the railway on corridor land.15-Feb-2017
81No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 5 hereof without the prior approval of the operator of the railway on corridor land.15-Feb-2017
91The Licensee not excavating, drilling, installing, erecting, depositing or permitting to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 5 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of the State Mining Engineer, DMP.15-Feb-2017
101No explosives being used or stored within one hundred and fifty (150) metres of the rail corridor land without the prior written consent of the Director, Dangerous Goods Safety Branch, DMP.15-Feb-2017
111The rights of ingress to and egress from the rail corridor land being at all times preserved to the employees, contractors and agents of the operator of the railway on corridor land, and the Public Transport Authority of WA.15-Feb-2017
121Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the rail corridor land.15-Feb-2017
131The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any exploration activities on Unnumbered Reserve 11.15-Feb-2017
141No interference with the transmission line or the installations in connection therewith, and the rights of ingress to and egress from the facility being at all times preserved to the owners thereof.15-Feb-2017
1In respect to the area designated as FNA 4787 in Tengraph the following additional condition applies:15-Feb-2017
151No exploration activities without the prior written approval of the Shire of Coolgardie.15-Feb-2017

Endorsements

Cond #VerTextStartEnd
11All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program.15-Feb-2017
21Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations.15-Feb-2017
31The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment.15-Feb-2017
41The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-
  • the grant of the Licence; or
  • registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer.
15-Feb-2017
51No mining within 30 metres of either side and to a depth of 15 metres of the Rail Corridor Land RCL/15 (Kalgoorlie West to Mount Walton Road) as shown in TENGRAPH without the prior written approval of the Minister responsible for the Mining Act 1978.15-Feb-2017
61No surface excavation approaching closer to the boundary of the Safety Zone established by Condition 5  hereof than a distance equal to three times the depth of the excavation without the prior written approval of the State Mining Engineer, DMP.15-Feb-2017
71Mining below 15 metres from the natural surface of the land in the Safety Zone established in Condition 5 hereof being approved by the State Mining Engineer, DMP in consultation with the operator of the railway on corridor land.15-Feb-2017
81No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 5 hereof without the prior approval of the operator of the railway on corridor land.15-Feb-2017
91The Licensee not excavating, drilling, installing, erecting, depositing or permitting to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 5 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of the State Mining Engineer, DMP.15-Feb-2017
101No explosives being used or stored within one hundred and fifty (150) metres of the rail corridor land without the prior written consent of the Director, Dangerous Goods Safety Branch, DMP.15-Feb-2017
111The rights of ingress to and egress from the rail corridor land being at all times preserved to the employees, contractors and agents of the operator of the railway on corridor land, and the Public Transport Authority of WA.15-Feb-2017
121Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the rail corridor land.15-Feb-2017
131The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any exploration activities on Unnumbered Reserve 11.15-Feb-2017
141No interference with the transmission line or the installations in connection therewith, and the rights of ingress to and egress from the facility being at all times preserved to the owners thereof.15-Feb-2017
1In respect to the area designated as FNA 4787 in Tengraph the following additional condition applies:15-Feb-2017
151No exploration activities without the prior written approval of the Shire of Coolgardie.15-Feb-2017

Dealings

TypeNumberDetails
Amalgamation501415Lodged:15:35 20 February 2017Amalgamating:Portion of former P 15/4827Situated within:External boundaries of E 15/1531Granted 18/08/2017 in respect to P 15/4827
Amalgamation501416Lodged:15:35 20 February 2017Amalgamating:Portion of former P 15/4828Situated within:External boundaries of E 15/1531Granted 18/08/2017 in respect to P 15/4828
Application to Amend558242Lodged:15:10 10 July 2019Amending:Address (Including DTC Details)From:Principal Place of Business : EVOLUTION MINING (MUNGARI) PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxx997 and DTC :EVOLUTION MINING (MUNGARI) PTY LTD, MCMAHON MINING TITLE SERVICES PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxx997To:Principal Place of Business : EVOLUTION MINING (MUNGARI) PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxxxxxxxx997 and DTC :EVOLUTION MINING (MUNGARI) PTY LTD, MCMAHON MINING TITLE SERVICES PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxxxxxxxx997RECORDED:15:10 10 July 2019

Payments

TypeYearReceipt DateReceipt No.MR LodgedAmountRental AreaEffective DateAmt DueDiscrepancy
Rental202122-Jan-2020 10130434$699.003 BL15-Feb-2017 $699.00$0.00
Rental202024-Jan-2019 10083552$408.003 BL15-Feb-2017 $408.00$0.00
Rental201931-Jan-2018 9017108896$402.003 BL15-Feb-2017 $402.00$0.00
Rental201816-Jun-2016 616817441374$375.753 BL15-Feb-2017 $375.75$0.00

Expenditure

YearForm 5 TypeMin ExpdExp Lodged DateTotal ExpdExemp NoExemp LodgedExemp AmtExemp StatusOutcome DateExploration ActivitiesMining ActivitiesAboriginal SurveyRentAdministrationProspectingStrike Through
2021$20,000.00false
2020$15,000.0002-Apr-2020 $60,514.00$49,855.00$0.00$0.00$845.00$9,814.00$0.00false
2019$15,000.0026-Mar-2019 $32,889.00$26,726.00$0.00$10.00$808.00$5,345.00$0.00false
2018$15,000.0022-Mar-2018 $23,921.00$19,087.00$0.00$0.00$1,017.00$3,817.00$0.00false

Native Title Referrals

Referred to Native Title DateReferral TypeCurrent StatusProcedureDetailsObjectionsWater CommentsDetermination AreasClaimsRepresentative Area Bodies
20-Mar-2017 Tenement AmalgamationExpedited Procedure : Native Title Cleared - Expedited AppliesExpedited Procedure2017-04-052017-08-05CLEARED - Expedited Applies2017-08-1825.1 HA305058S1211350E15km NE'ly of Coolgardie13GoldfieldsNative Title Services Goldfields
20-Mar-2017 Tenement AmalgamationExpedited Procedure : Native Title Cleared - Expedited AppliesExpedited Procedure2017-04-052017-08-05CLEARED - Expedited Applies2017-08-1811.77 HA305058S1211439E15km NE'ly of Coolgardie13GoldfieldsNative Title Services Goldfields
25-Aug-2016 Tenement ApplicationExpedited Procedure : Native Title Cleared - Expedited AppliesExpedited Procedure2016-09-212017-01-21CLEARED - Expedited Applies2017-02-143 BL30500S121140E15km NE'ly of Coolgardie13GoldfieldsNative Title Services Goldfields