Cache entry for E 08/2799

Extracted from MTO on 23-Sep-2020 03:34, last changed 16-Jul-2020.

Tenement Summary

Identifier:E 08/2799Type:Exploration Licence
Status:LiveDistrict:ASHBURTON M.F.
Lodged:ONLINEArea:101 BL
Purposes:Term:5 Years
Markout:Received:09-Dec-2015 13:00
Commence:06-Apr-2020 Expiry:05-Apr-2025

Holders

Company NameSharesTotal Shares
WYLOO METALS PTY LTD100100

Applicants on Receival

Company NameSharesTotal Shares
SQUADRON RESOURCES PTY LTD100100

Shires

Shire NameShire NumberStartArea
ASHBURTON SHIRE25009-Dec-2015 101.00000 BL

Conditions

#VerTextStartEnd
11All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety.06-Apr-2020
21All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program.06-Apr-2020
31Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations.06-Apr-2020
41The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment.06-Apr-2020
51The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-
  • the grant of the Licence; or
  • registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer.
06-Apr-2020
61No interference with Geodetic Survey Stations SSM-YANREY 54 and SSM-YANREY 55 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface.06-Apr-2020
71No interference with the use of the Aerial Landing Ground and mining thereon being confined to below a depth of 15 metres from the natural surface.06-Apr-2020
81No interference with the transmission line or the installations in connection therewith, and the rights of ingress to and egress from the facility being at all times preserved to the owners thereof.06-Apr-2020
91Mining on a strip of land 20 metres wide with any pipeline as the centreline being confined to below a depth of 31 metres from the natural surface and no mining material being deposited upon such strip and the rights of ingress to and egress from the facility being at all times preserved to the owners thereof.06-Apr-2020
101Prior to the cessation of exploration/prospecting activity the licensee notifying the Environmental Officer, DMIRS and arranging an inspection as required.06-Apr-2020
111No mining within 25 metres of either side of the petroleum pipeline licence area of PL16, 19 and 103 and to a depth of 50 metres being the Consultation Area as shown in TENGRAPH, without the mining tenement holder and the petroleum pipeline licensee consulting with each other and reaching agreement on access and mining activities to be undertaken within the Consultation Area.06-Apr-2020
121No surface excavation approaching closer to the boundary of the Consultation Area than a distance equal to three times the depth of the excavation without the mining tenement holder and the petroleum pipeline licensee reaching agreement as to a lesser distance.06-Apr-2020
131No explosives being used or stored within 150 metres of the petroleum licence area without the mining tenement holder and the petroleum pipeline licensee reaching agreement as to a lesser distance.06-Apr-2020
141The rights of ingress to and egress from the petroleum pipeline licence area being at all times preserved for the employees, contractors and agents of the owners and operators of the pipeline.06-Apr-2020
151Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purposes of protecting the pipeline and any existing condition imposed for this purpose may be cancelled or varied.06-Apr-2020
1In respect to the area designated as CPL 38 in TENGRAPH the following conditions apply:06-Apr-2020
161Prior to any ground-disturbing activity, as defined by the Executive Director, Resource and Environmental Compliance, Department of Mines, Industry Regulation and Safety (DMIRS) the licensee preparing a detailed program for each phase of proposed exploration for approval of the Executive Director, Resource and Environmental Compliance, DMIRS. The program to include:
  • maps and/or aerial photographs showing all proposed routes, construction and upgrading of tracks, camps, drill sites and any other disturbances;
  • the purpose, specifications and life of all proposed disturbances;
  • proposals which may disturb any declared rare or geographically restricted flora and fauna; and
  • techniques, prescriptions and timetable for the rehabilitation of all proposed disturbances
06-Apr-2020
171The licensee, at their expense, rehabilitating all areas cleared, explored or otherwise disturbed during the term of the licence to the satisfaction of the Executive Director, Resource and Environmental Compliance, DMIRS. Such rehabilitation as is appropriate and may include:
  • stockpiling and return of topsoil;
  • backfilling all holes, trenches and costeans;
  • ripping;
  • contouring to the original landform;
  • revegetation with seed; and
  • capping and backfilling of all drill holes.
06-Apr-2020

Endorsements

Cond #VerTextStartEnd
11All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety.06-Apr-2020
21All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program.06-Apr-2020
31Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations.06-Apr-2020
41The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment.06-Apr-2020
51The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-
  • the grant of the Licence; or
  • registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer.
06-Apr-2020
61No interference with Geodetic Survey Stations SSM-YANREY 54 and SSM-YANREY 55 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface.06-Apr-2020
71No interference with the use of the Aerial Landing Ground and mining thereon being confined to below a depth of 15 metres from the natural surface.06-Apr-2020
81No interference with the transmission line or the installations in connection therewith, and the rights of ingress to and egress from the facility being at all times preserved to the owners thereof.06-Apr-2020
91Mining on a strip of land 20 metres wide with any pipeline as the centreline being confined to below a depth of 31 metres from the natural surface and no mining material being deposited upon such strip and the rights of ingress to and egress from the facility being at all times preserved to the owners thereof.06-Apr-2020
101Prior to the cessation of exploration/prospecting activity the licensee notifying the Environmental Officer, DMIRS and arranging an inspection as required.06-Apr-2020
111No mining within 25 metres of either side of the petroleum pipeline licence area of PL16, 19 and 103 and to a depth of 50 metres being the Consultation Area as shown in TENGRAPH, without the mining tenement holder and the petroleum pipeline licensee consulting with each other and reaching agreement on access and mining activities to be undertaken within the Consultation Area.06-Apr-2020
121No surface excavation approaching closer to the boundary of the Consultation Area than a distance equal to three times the depth of the excavation without the mining tenement holder and the petroleum pipeline licensee reaching agreement as to a lesser distance.06-Apr-2020
131No explosives being used or stored within 150 metres of the petroleum licence area without the mining tenement holder and the petroleum pipeline licensee reaching agreement as to a lesser distance.06-Apr-2020
141The rights of ingress to and egress from the petroleum pipeline licence area being at all times preserved for the employees, contractors and agents of the owners and operators of the pipeline.06-Apr-2020
151Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purposes of protecting the pipeline and any existing condition imposed for this purpose may be cancelled or varied.06-Apr-2020
1In respect to the area designated as CPL 38 in TENGRAPH the following conditions apply:06-Apr-2020
161Prior to any ground-disturbing activity, as defined by the Executive Director, Resource and Environmental Compliance, Department of Mines, Industry Regulation and Safety (DMIRS) the licensee preparing a detailed program for each phase of proposed exploration for approval of the Executive Director, Resource and Environmental Compliance, DMIRS. The program to include:
  • maps and/or aerial photographs showing all proposed routes, construction and upgrading of tracks, camps, drill sites and any other disturbances;
  • the purpose, specifications and life of all proposed disturbances;
  • proposals which may disturb any declared rare or geographically restricted flora and fauna; and
  • techniques, prescriptions and timetable for the rehabilitation of all proposed disturbances
06-Apr-2020
171The licensee, at their expense, rehabilitating all areas cleared, explored or otherwise disturbed during the term of the licence to the satisfaction of the Executive Director, Resource and Environmental Compliance, DMIRS. Such rehabilitation as is appropriate and may include:
  • stockpiling and return of topsoil;
  • backfilling all holes, trenches and costeans;
  • ripping;
  • contouring to the original landform;
  • revegetation with seed; and
  • capping and backfilling of all drill holes.
06-Apr-2020

Dealings

TypeNumberDetails
Application to Amend490197Lodged:13:09:24 07 July 2016Amending:Address (Including DTC Details)From:SQUADRON RESOURCES PTY LTD, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849To:SQUADRON RESOURCES PTY LTD, HETHERINGTON EXPLORATION & MINING TITLE SERVICES (WA) PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxx977RECORDED:13:09:24 07 July 2016
Application to Amend531446Lodged:15:47:31 29 May 2018Amending:Address (Including DTC Details)From:SQUADRON RESOURCES PTY LTD, HETHERINGTON EXPLORATION & MINING TITLE SERVICES (WA) PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxx977To:SQUADRON RESOURCES PTY LTD, HETHERINGTON EXPLORATION & MINING TITLE SERVICES (WA) PTY LTD, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES (WA) PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxx977RECORDED:15:47:31 29 May 2018
Application to Amend554325Lodged:15:35 21 May 2019Amending:Address (Including DTC Details)From:Principal Place of Business : SQUADRON RESOURCES PTY LTD, SAME AS CORRESPONDENCE and DTC :SQUADRON RESOURCES PTY LTD, HETHERINGTON EXPLORATION & MINING TITLE SERVICES (WA) PTY LTD, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES (WA) PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxx977To:Principal Place of Business : SQUADRON RESOURCES PTY LTD, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849 and DTC :SQUADRON RESOURCES PTY LTD, HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxxx977RECORDED:15:35 21 May 2019
Application to Amend581636Lodged:11:28:02 08 July 2020Amending:NameFrom:SQUADRON RESOURCES PTY LTDTo:WYLOO METALS PTY LTDREJECTED:11:28:02 08 July 2020
Application to Amend581792Lodged:08:30 10 July 2020Amending:NameFrom:SQUADRON RESOURCES PTY LTDTo:WYLOO METALS PTY LTDRECORDED:08:30 10 July 2020

Payments

TypeYearReceipt DateReceipt No.MR LodgedAmountRental AreaEffective DateAmt DueDiscrepancy
Rental202109-Dec-2015 534316491515$12,650.25101 BL06-Apr-2020 $12,650.25$0.00

Expenditure

YearForm 5 TypeMin ExpdExp Lodged DateTotal ExpdExemp NoExemp LodgedExemp AmtExemp StatusOutcome DateExploration ActivitiesMining ActivitiesAboriginal SurveyRentAdministrationProspectingStrike Through
2021$101,000.00false

Native Title Referrals

Referred to Native Title DateReferral TypeCurrent StatusProcedureDetailsObjectionsWater CommentsDetermination AreasClaimsRepresentative Area Bodies
01-Nov-2019 Tenement ApplicationExpedited Procedure : Native Title Cleared - Expedited AppliesExpedited Procedure2019-11-202020-03-20CLEARED - Expedited Applies2020-04-03101 BL22738S115841E54.3km S'ly of OnslowTHALANYJI(WCD2008/003)WC1999/045WAD6113/1998falseWCD2008/003116EXISTNo12PilbaraYamatji Marlpa Aboriginal Corporation