Tenement Summary

Identifier:E 08/2703-IType:Exploration Licence
Status:LiveDistrict:ASHBURTON M.F.
Lodged:ONLINEArea:9 BL
Purposes:Term:5 Years
Markout:Received:17-Feb-2015 09:32
Commence:22-Apr-2016 Expiry:21-Apr-2021

Holders

Company NameCorrespondence AddressSharesTotal Shares
POLARIS METALS PTY LTDC/- TENEMENT MANAGER, PO BOX 1095, CANNING BRIDGE LPO, APPLECROSS, WA, 6153100100

Applicants on Receival

Company NameCorrespondence AddressSharesTotal Shares
POLARIS METALS PTY LTDC/- TENEMENT MANAGER, PO BOX 1095, CANNING BRIDGE LPO, APPLECROSS, WA, 6153100100

Shires

Shire NameShire NumberStartArea
ASHBURTON SHIRE25017-Feb-2015 9.00000 BL

Conditions

#VerTextStartEnd
11All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program.22-Apr-2016
21Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations.22-Apr-2016
31The licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment.22-Apr-2016
41The licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-
  • the grant of the licence; or
  • registration of a transfer introducing a new licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer.
22-Apr-2016
51No activities being carried out within the proposed railway corridor (designated FNA 9198 ) that interfere with or restrict any rail route investigation activities being undertaken by the rail line proponent.22-Apr-2016
61No interference with Geodetic Survey Stations WYLOO 61, 63T, 63, 64 and 64T and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface.22-Apr-2016
71No mining within 25 metres of either side of the Gas/Petroleum pipeline contained within Petroleum Pipeline Licence No  24  as shown in TENGRAPH.22-Apr-2016
81No surface excavation approaching closer to the boundary of the Safety Zone established by condition 7 hereof than a distance equal to three times the depth of the excavation without the prior written approval of the Director Petroleum DMP22-Apr-2016
91No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 7 hereof without the prior approval of the operators of the Gas/Petroleum pipeline.22-Apr-2016
101The licensee shall not excavate, drill, install, erect, deposit or permit to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 7 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of the Director Petroleum DMP22-Apr-2016
111No explosives being used or stored within one hundred and fifty (150) metres of the Gas/Petroleum pipeline without the prior written consent of the Director Petroleum DMP.22-Apr-2016
121Mining on the Safety Zone established in Condition 7 hereof being confined to below a depth of 50 metres from the natural surface unless otherwise approved by the Director Petroleum DMP .22-Apr-2016
131The rights of ingress to and egress from the pipeline easement established in Condition 7 hereof being at all times preserved for employees, contractors and agents of the operators of the Gas/Petroleum pipeline.22-Apr-2016
141Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the Gas/Petroleum pipeline.22-Apr-2016

Endorsements

Cond #VerTextStartEnd
11All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program.22-Apr-2016
21Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations.22-Apr-2016
31The licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment.22-Apr-2016
41The licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-
  • the grant of the licence; or
  • registration of a transfer introducing a new licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer.
22-Apr-2016
51No activities being carried out within the proposed railway corridor (designated FNA 9198 ) that interfere with or restrict any rail route investigation activities being undertaken by the rail line proponent.22-Apr-2016
61No interference with Geodetic Survey Stations WYLOO 61, 63T, 63, 64 and 64T and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface.22-Apr-2016
71No mining within 25 metres of either side of the Gas/Petroleum pipeline contained within Petroleum Pipeline Licence No  24  as shown in TENGRAPH.22-Apr-2016
81No surface excavation approaching closer to the boundary of the Safety Zone established by condition 7 hereof than a distance equal to three times the depth of the excavation without the prior written approval of the Director Petroleum DMP22-Apr-2016
91No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 7 hereof without the prior approval of the operators of the Gas/Petroleum pipeline.22-Apr-2016
101The licensee shall not excavate, drill, install, erect, deposit or permit to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 7 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of the Director Petroleum DMP22-Apr-2016
111No explosives being used or stored within one hundred and fifty (150) metres of the Gas/Petroleum pipeline without the prior written consent of the Director Petroleum DMP.22-Apr-2016
121Mining on the Safety Zone established in Condition 7 hereof being confined to below a depth of 50 metres from the natural surface unless otherwise approved by the Director Petroleum DMP .22-Apr-2016
131The rights of ingress to and egress from the pipeline easement established in Condition 7 hereof being at all times preserved for employees, contractors and agents of the operators of the Gas/Petroleum pipeline.22-Apr-2016
141Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the Gas/Petroleum pipeline.22-Apr-2016

Payments

TypeYearReceipt DateReceipt No.MR LodgedAmountRental AreaEffective DateAmt DueDiscrepancy
Rental201813-Apr-2017 MT-210011001748-EF$1,165.509 BL22-Apr-2016 $1,165.50$0.00
Rental201717-Feb-2015 504812535355$1,098.909 BL22-Apr-2016 $1,098.90$0.00

Expenditure

YearForm 5 TypeMin ExpdExp Lodged DateTotal ExpdExemp NoExemp LodgedExemp AmtExemp StatusOutcome DateExploration ActivitiesMining ActivitiesAboriginal SurveyRentAdministrationProspectingStrike Through
2018$20,000.00false
2017$20,000.0019-Jun-2017 $24,935.00$18,491.00$0.00$0.00$2,444.00$4,000.00$0.00false

Native Title Referrals

Referred to Native Title DateReferral TypeCurrent StatusProcedureDetailsObjectionsWater CommentsDetermination AreasClaimsRepresentative Area Bodies
18-Nov-2015 Tenement ApplicationExpedited Procedure : Native Title Cleared - Expedited AppliesExpedited Procedure2015-12-022016-04-02CLEARED - Expedited Applies2016-04-209 BL225030S116380E114km W'ly of ParaburdooWO2016/00762016-02-23WC2001/005Objection Withdrawn Agreement2016-03-22Puutu Kunti Kurrama People and Pinikura People #1 and #2(WCD2015/003)WC2001/005WAD6007/2001falseWCD2015/003BOTHNoPuutu Kunti Kurrama and Pinikura(WC2001/005)WC2001/005WAD6007/2001falseDeterminedPuutu Kunti Kurrama and Pinikura 2(WC2005/004)WC2005/004WAD126/2005falseDetermined12PilbaraYamatji Marlpa Aboriginal Corporation