Cache entry for E 08/1196

Extracted from MTO on 22-Sep-2017 03:36, last changed 29-Jun-2017.

Tenement Summary

Identifier:E 08/1196-IType:Exploration Licence
Status:LiveDistrict:ASHBURTON M.F.
Lodged:KARRATHAArea:32 BL
Purposes:Term:5 Years (Extended)
Markout:Received:19-Jun-2000 09:00
Commence:06-Feb-2001 Expiry:05-Feb-2018

Holders

Company NameCorrespondence AddressSharesTotal Shares
MITSUI IRON ORE DEVELOPMENT PTY LTDC/- JOHN SMITH, GENERAL MANAGER ADMINISTRATION GPO BOX 2585, PERTH, WA, 600140200
NORTH MINING LIMITEDC/- RIO TINTO IRON ORE, LAND ASSETS DEPARTMENT GPO BOX A42, PERTH, WA, 683770200
ROBE RIVER MINING CO. PTY LIMITEDC/- RIO TINTO IRON ORE TENURE MANAGEMENT & STRATEGY, GPO BOX A42, PERTH, WA, 683760200
CAPE LAMBERT IRON ASSOCIATES (REGISTERED BUSINESS NAME)C/- JOHN SMITH, GENERAL MANAGER ADMINISTRATION GPO BOX 2585, PERTH, WA, 600110200
PANNAWONICA IRON ASSOCIATES (REGISTERED BUSINESS NAME)C/- JOHN SMITH, GENERAL MANAGER ADMINISTRATION GPO BOX 2585, PERTH, WA, 600120200

Applicants on Receival

Company NameCorrespondence AddressSharesTotal Shares
MITSUI IRON ORE DEVELOPMENT PTY LTDC/- JOHN SMITH, GENERAL MANAGER ADMINISTRATION GPO BOX 2585, PERTH, WA, 600140200
NORTH MINING LIMITEDC/- RIO TINTO IRON ORE, LAND ASSETS DEPARTMENT GPO BOX A42, PERTH, WA, 683770200
ROBE RIVER MINING CO. PTY LIMITEDC/- RIO TINTO IRON ORE, LAND ASSETS DEPARTMENT GPO BOX A42, PERTH, WA, 683760200
CAPE LAMBERT IRON ASSOCIATES (REGISTERED BUSINESS NAME)C/- JOHN SMITH, GENERAL MANAGER ADMINISTRATION GPO BOX 2585, PERTH, WA, 600110200
PANNAWONICA IRON ASSOCIATES (REGISTERED BUSINESS NAME)C/- JOHN SMITH, GENERAL MANAGER ADMINISTRATION GPO BOX 2585, PERTH, WA, 600120200

Relationships

Relationship TypeDealingDealing StatusTenementTenement Status
Section 67Conversion 232970FinalisedM 08/434Dead
Section 67Conversion 232971FinalisedM 08/435Dead
Section 67Conversion 232973FinalisedM 08/436Dead
Section 67Conversion 232975FinalisedM 08/437Dead
Section 67Conversion 232977FinalisedM 08/438Dead
Section 67Conversion 232979FinalisedM 08/439Dead
Section 67Conversion 232981FinalisedM 08/440Dead
Section 67Conversion 232983FinalisedM 08/441Dead
Section 67Conversion 233028FinalisedM 08/429Dead
Section 67Conversion 233029FinalisedM 08/430Dead
Section 67Conversion 233030FinalisedM 08/431Dead
Section 67Conversion 233031FinalisedM 08/432Dead
Section 67Conversion 237167FinalisedM 08/433Dead
Amalgamation (Same Holder)Amalgamation 311664GrantedP 08/538Dead
Amalgamation (Same Holder)Amalgamation 311664GrantedP 08/547-IDead

Shires

Shire NameShire NumberStartArea
ASHBURTON SHIRE25019-Jun-2000 32.00000 BL

Conditions

#VerTextStartEnd
11All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe after completion.06-Feb-2001
22All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DOIR.27-Oct-2004
21All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the District Mining Engineer. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the District Mining Engineer.06-Feb-2001 26-Oct-2004
31All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration programme.06-Feb-2001
42Unless the written approval of the Environmental Officer is first obtained, the use of scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations.27-Oct-2004
41Unless the written approval of the District Mining Engineer is first obtained, the use of scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations.06-Feb-2001 26-Oct-2004
51The licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment.06-Feb-2001
61The licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-
  • the grant of the licence; or
  • registration of a transfer introducing a new licensee.
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer.
06-Feb-2001
71No excavation, excepting shafts, approaching closer to the North West Coastal Highway, Highway verge or the road reserve than a distance equal to twice the depth of the excavation and mining on the North West Coastal Highway or Highway verge being confined to below a depth of 30 metres from the natural surface, and on any other road or road verge, to below a depth of 15 metres from the natural surface.06-Feb-2001
81No interference with Geodetic Survey Stations Yarraloola 18 and 19 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface.06-Feb-2001
91No interference with the use of the optic fibre cable or the installations in connection therewith, and the rights of ingress to and egress from the facility being at all times preserved to the owners thereof.06-Feb-2001
101No mining within 25 metres of either side of the Dampier to Perth/Bunbury Gas Pipeline.06-Feb-2001
111No surface excavation approaching closer to the boundary of the Safety Zone established by Condition 10 hereof than a distance equal to three times the depth of the excavation without the prior written approval of the State Mining Engineer.06-Feb-2001
121No interference with the drainage pattern, and no parking, storage, or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 10 hereof without the prior approval of the operators of the Dampier to Perth/Bunbury Gas Pipeline.06-Feb-2001
131The licensee shall not excavate, drill, install, erect, deposit or permit to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 10 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of the State Mining Engineer.06-Feb-2001
141No explosives being used or stored within one hundred and fifty (150) metres of the Dampier to Perth/Bunbury Gas Pipeline without the prior written consent of the State Mining Engineer.06-Feb-2001
151Mining on the Safety Zone established in Condition 10 hereof being confined to below a depth of 50 metres from the natural surface unless otherwise approved by the State Mining Engineer.06-Feb-2001
161The rights of ingress to and egress from the Dampier to Perth/Bunbury Gas Pipeline Easement being at all times preserved for employees, contractors and agents of the operators of the Dampier to Perth/Bunbury Gas Pipeline.06-Feb-2001
171Such further conditions as may from time to time be imposed by the Minister for Mines for the purpose of protecting the Dampier to Perth/Bunbury Gas Pipeline.06-Feb-2001
182The construction and operation of the project and measures to protect the environment being carried out generally in accordance with the document titled:
  • "Programme of Works for Robe River Mining on E08/1196, E08/1416, E08/788 (Exp 5411)" dated 25 September 2006 signed by Ganesh Krishnamurthy and retained on Department of Industry and Resources File No. 9098/00Vol01;
  • (Reg. ID 32393) "Programme of Work on E08/1196 for Rio Tinto Iron Ore Pty Ltd" dated 13 September 2011 signed by Trent Woods and retained on Department of Mines and Petroleum file No. 32393.
Where a difference exists between the above document(s) and the following conditions, then the following conditions shall prevail.
17-Nov-2011
181The construction and operation of the project and measures to protect the environment being carried out generally in accordance with the document titled:
  • "Programme of Works for Robe River Mining on E08/1196, E08/1416, E08/788 (Exp 5411)" dated 25 September 2006 signed by Ganesh Krishnamurthy and retained on Department of Industry and Resources File No. 9098/00Vol01
Where a difference exists between the above document(s) and the following conditions, then the following conditions shall prevail.
07-May-2007 16-Nov-2011
191The development and operation of the project being carried out in such a manner so as to create the minimum practicable disturbance to the existing vegetation and natural landform.07-May-2007
201The licensee arranging lodgement of an Unconditional Performance Bond executed by a Bank or other approved financial institution in favour of the Minister responsible for the Mining Act 1978 for due compliance with the environmental conditions of the licence in the sum of:
  • $34,000.
07-May-2007 17-Nov-2011
211All topsoil and vegetation being removed ahead of all mining operations and being stockpiled appropriately for later respreading or immediately respread as rehabilitation progresses.17-Nov-2011

Endorsements

Cond #VerTextStartEnd
11All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe after completion.06-Feb-2001
22All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DOIR.27-Oct-2004
21All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the District Mining Engineer. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the District Mining Engineer.06-Feb-2001 26-Oct-2004
31All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration programme.06-Feb-2001
42Unless the written approval of the Environmental Officer is first obtained, the use of scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations.27-Oct-2004
41Unless the written approval of the District Mining Engineer is first obtained, the use of scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations.06-Feb-2001 26-Oct-2004
51The licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment.06-Feb-2001
61The licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-
  • the grant of the licence; or
  • registration of a transfer introducing a new licensee.
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer.
06-Feb-2001
71No excavation, excepting shafts, approaching closer to the North West Coastal Highway, Highway verge or the road reserve than a distance equal to twice the depth of the excavation and mining on the North West Coastal Highway or Highway verge being confined to below a depth of 30 metres from the natural surface, and on any other road or road verge, to below a depth of 15 metres from the natural surface.06-Feb-2001
81No interference with Geodetic Survey Stations Yarraloola 18 and 19 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface.06-Feb-2001
91No interference with the use of the optic fibre cable or the installations in connection therewith, and the rights of ingress to and egress from the facility being at all times preserved to the owners thereof.06-Feb-2001
101No mining within 25 metres of either side of the Dampier to Perth/Bunbury Gas Pipeline.06-Feb-2001
111No surface excavation approaching closer to the boundary of the Safety Zone established by Condition 10 hereof than a distance equal to three times the depth of the excavation without the prior written approval of the State Mining Engineer.06-Feb-2001
121No interference with the drainage pattern, and no parking, storage, or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 10 hereof without the prior approval of the operators of the Dampier to Perth/Bunbury Gas Pipeline.06-Feb-2001
131The licensee shall not excavate, drill, install, erect, deposit or permit to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 10 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of the State Mining Engineer.06-Feb-2001
141No explosives being used or stored within one hundred and fifty (150) metres of the Dampier to Perth/Bunbury Gas Pipeline without the prior written consent of the State Mining Engineer.06-Feb-2001
151Mining on the Safety Zone established in Condition 10 hereof being confined to below a depth of 50 metres from the natural surface unless otherwise approved by the State Mining Engineer.06-Feb-2001
161The rights of ingress to and egress from the Dampier to Perth/Bunbury Gas Pipeline Easement being at all times preserved for employees, contractors and agents of the operators of the Dampier to Perth/Bunbury Gas Pipeline.06-Feb-2001
171Such further conditions as may from time to time be imposed by the Minister for Mines for the purpose of protecting the Dampier to Perth/Bunbury Gas Pipeline.06-Feb-2001
182The construction and operation of the project and measures to protect the environment being carried out generally in accordance with the document titled:
  • "Programme of Works for Robe River Mining on E08/1196, E08/1416, E08/788 (Exp 5411)" dated 25 September 2006 signed by Ganesh Krishnamurthy and retained on Department of Industry and Resources File No. 9098/00Vol01;
  • (Reg. ID 32393) "Programme of Work on E08/1196 for Rio Tinto Iron Ore Pty Ltd" dated 13 September 2011 signed by Trent Woods and retained on Department of Mines and Petroleum file No. 32393.
Where a difference exists between the above document(s) and the following conditions, then the following conditions shall prevail.
17-Nov-2011
181The construction and operation of the project and measures to protect the environment being carried out generally in accordance with the document titled:
  • "Programme of Works for Robe River Mining on E08/1196, E08/1416, E08/788 (Exp 5411)" dated 25 September 2006 signed by Ganesh Krishnamurthy and retained on Department of Industry and Resources File No. 9098/00Vol01
Where a difference exists between the above document(s) and the following conditions, then the following conditions shall prevail.
07-May-2007 16-Nov-2011
191The development and operation of the project being carried out in such a manner so as to create the minimum practicable disturbance to the existing vegetation and natural landform.07-May-2007
201The licensee arranging lodgement of an Unconditional Performance Bond executed by a Bank or other approved financial institution in favour of the Minister responsible for the Mining Act 1978 for due compliance with the environmental conditions of the licence in the sum of:
  • $34,000.
07-May-2007 17-Nov-2011
211All topsoil and vegetation being removed ahead of all mining operations and being stockpiled appropriately for later respreading or immediately respread as rehabilitation progresses.17-Nov-2011

Dealings

TypeNumberDetails
Miscellaneous EntryNippon Steel Australia Pty Limited (6/200th shares) Sumitomo Metal Australia Pty Ltd (2/200th shares) Mitsui Iron Ore Development Pty Ltd (2/200th shares) as joint tenants carrying on business in partnership under the registered business name "Cape Lambert Iron Associates" Nippon Steel Australia Pty Limited (15/200th shares) Sumitomo Metal Australia Pty Ltd (5/200th shares) as joint tenants carrying on business in partnership under the registered business name "Pannawonica Iron Associates"
Exemption from Drop-off129H/034Lodged 2:37:00 PM on 20 Jan 2004 applying for relief from the provisions of Section 65(1)(a)GRANTED 11 Feb 2004
Exemption from Drop-off130H/034Lodged 9:30:00 AM on 22 Jan 2004LAPSED 11 Feb 2004 in favour of and identical to application 129H/034
Exemption from Drop-off179H/045Lodged 12:00 AM on 27 Jan 2005 applying for relief from the provisions of Section 65(1)(b)GRANTED 08 Feb 2005
Extension / Renewal of TermKR98/056Lodged 10:28:00 AM on 14 Dec 2005 applied for a period of 2 YearsRECORDED 10:28 AM 14 Dec 2005GRANTED 05 Apr 2006 for a further period of 2 Years
Conversion232971Lodged 8:30:00 AM on 08 Feb 2006 M 08/435 applied for pursuant to Section 67.RECORDED 8:30 AM 08 Feb 2006Discontinued due to M 08/435 Withdrawn 12:03 21 June 2010
Conversion232973Lodged 8:30:00 AM on 08 Feb 2006 M 08/436 applied for pursuant to Section 67.RECORDED 8:30 AM 08 Feb 2006Discontinued due to M 08/436 Withdrawn 12:03 21 June 2010
Conversion232975Lodged 8:30:00 AM on 08 Feb 2006 M 08/437 applied for pursuant to Section 67.RECORDED 8:30 AM 08 Feb 2006Discontinued due to M 08/437 Withdrawn 14:50 30 March 2010
Conversion232977Lodged 8:30:00 AM on 08 Feb 2006 M 08/438 applied for pursuant to Section 67.RECORDED 8:30 AM 08 Feb 2006Discontinued due to M 08/438 Withdrawn 14:50 30 March 2010
Conversion232979Lodged 8:30:00 AM on 08 Feb 2006 M 08/439 applied for pursuant to Section 67.RECORDED 8:30 AM 08 Feb 2006Discontinued due to M 08/439 Withdrawn 14:50 30 March 2010
Conversion233028Lodged 8:30:00 AM on 08 Feb 2006 M 08/429 applied for pursuant to Section 67.RECORDED 8:30 AM 08 Feb 2006Discontinued due to M 08/429 Withdrawn 12:03 21 June 2010
Conversion233029Lodged 8:30:00 AM on 08 Feb 2006 M 08/430 applied for pursuant to Section 67.RECORDED 8:30 AM 08 Feb 2006Discontinued due to M 08/430 Withdrawn 14:50 30 March 2010
Conversion233030Lodged 8:30:00 AM on 08 Feb 2006 M 08/431 applied for pursuant to Section 67.RECORDED 8:30 AM 08 Feb 2006Discontinued due to M 08/431 Withdrawn 12:03 21 June 2010
Conversion233031Lodged 8:30:00 AM on 08 Feb 2006 M 08/432 applied for pursuant to Section 67.RECORDED 8:30 AM 08 Feb 2006Discontinued due to M 08/432 Withdrawn 14:50 30 March 2010
Conversion237167Lodged 8:30:00 AM on 08 Feb 2006 M08/433 applied for pursuant to Section 67.RECORDED 8:30 AM 08 Feb 2006Discontinued due to M 08/433 Withdrawn 12:03 21 June 2010
Conversion232970Lodged 8:30:00 AM on 08 Feb 2006 M 08/434 applied for pursuant to Section 67.RECORDED 8:30 AM 08 Feb 2006Discontinued due to M 08/434 Withdrawn 12:03 21 June 2010
Conversion232981Lodged 8:30:00 AM on 08 Feb 2006 M 08/440 applied for pursuant to Section 67.RECORDED 8:30 AM 08 Feb 2006LAPSED 18 Jan 2008 on the commencement of term of E08/1771 pursuant to Section 120AA and licence partially expired
Conversion232983Lodged 8:30:00 AM on 08 Feb 2006 M 08/441 applied for pursuant to Section 67.RECORDED 8:30 AM 08 Feb 2006LAPSED 18 Jan 2008 on the commencement of term of E08/1771 pursuant to Section 120AA and licence partially expired
Bond261237Lodged on 01 Mar 2007 For $34,000.00RECORDED 09 Mar 2007Lodged:00:00 01 March 2007Bond Type:Unconditional Performance BondBond Amount:$34,000.00RECORDED:09 March 2007RETIRED:17 November 2011
Bond Requirement307533Requirement Date:07/05/2007Amount:$34,000.00RECORDED:14:22:53 07 May 2007FINALISED:12:13:13 17 November 2011
Extension / Renewal of Term281090Lodged 11:09:00 AM on 28 Dec 2007 applied for a period of 2 YearsRECORDED 11:09 AM 28 Dec 2007GRANTED 01 Jul 2008 for a further period of 2 Years
Expiry - Partial226516in respect to Hamersley Range Block 1389 o, p, u, 1390 l, q, v contained in the granted boundaries of E08/1771 pursuant to S120AA.Retained Blocks:HAMERSLEY RANGE 1390 m, n, o, r, s, w, x HAMERSLEY RANGE 1462 b, c, g, h, j, k, m, n, o, p, r, s, t, u, x, y, z HAMERSLEY RANGE 1463 f, g, l, m, q, r, v, wRetained Total:32 BL.RECORDED 12.00 Midnight 18 Jan 2008EFFECTIVE:00:00:01 18 January 2008
Amalgamation311664Lodged:11:06 03 February 2009The partial live secondary tenements P08/538 and P08/547 to be amalgamated into primary tenement E08/1196. Granted 24/09/2009
Extension / Renewal of Term337950Lodged:11:50 30 December 2009Applied For Period:1 YearsGRANTED:23 November 2010Granted Period:1 YearsTerm Extended To:05/02/2011
Extension / Renewal of Term363009Lodged:12:03 11 January 2011Applied For Period:1 YearsRECORDED:12:03 11 January 2011GRANTED:21 January 2011Granted Period:1 YearsTerm Extended To:05/02/2012
Bond385089Lodged:13:00 11 November 2011Bond Type:Unconditional Performance BondBond Amount:$62,000.00RECORDED:17 November 2011RETIRED - MRF:27 October 2014
Bond Requirement385306Requirement Date:16/11/2011Amount:$62,000.00RECORDED:11:23:18 17 November 2011FINALISED:11:39:55 27 October 2014
Extension / Renewal of Term388249Lodged:12:20 23 December 2011Applied For Period:1 YearsRECORDED:12:20 23 December 2011GRANTED:26 June 2012Granted Period:1 YearsTerm Extended To:05/02/2013
Extension / Renewal of Term414028Lodged:15:00 21 December 2012Applied For Period:1 YearsRECORDED:15:00 21 December 2012GRANTED:17 April 2013Granted Period:1 YearsTerm Extended To:05/02/2014
Extension / Renewal of Term437737Lodged:08:40 24 December 2013Applied For Period:1 YearsRECORDED:08:40 24 December 2013GRANTED:01 April 2014Granted Period:1 YearsTerm Extended To:05/02/2015
Application to Amend444687Lodged:15:10 17 April 2014Amending:AddressFrom:ROBE RIVER MINING CO. PTY LTD, C/- RIO TINTO IRON ORE, LAND ASSETS DEPARTMENT GPO BOX A42, PERTH, WA, 6837To:ROBE RIVER MINING CO. PTY LTD, C/- RIO TINTO IRON ORE TENURE MANAGEMENT & STRATEGY, GPO BOX A42, PERTH, WA, 6837RECORDED:15:10 17 April 2014
Extension / Renewal of Term459768Lodged:14:00 24 December 2014Applied For Period:1 YearsRECORDED:14:00 24 December 2014GRANTED:28 April 2015Granted Period:1 YearsTerm Extended To:05/02/2016
Extension / Renewal of Term479467Lodged:15:01:21 23 December 2015Applied For Period:1 YearsRECORDED:15:01:21 23 December 2015GRANTED:31 May 2016Granted Period:1 YearsTerm Extended To:05/02/2017
Extension / Renewal of Term499023Lodged:13:48:16 22 December 2016Applied For Period:1 YearsRECORDED:13:48:16 22 December 2016GRANTED:16 March 2017Granted Period:1 YearsTerm Extended To:05/02/2018

Payments

TypeYearReceipt DateReceipt No.MR LodgedAmountRental AreaEffective DateAmt DueDiscrepancy
Rental201819-Dec-2016 MT-210010854923-EF$16,563.2032 BL18-Jan-2008 $16,563.20$0.00
Rental201715-Dec-2015 MT-210010455379-EF$16,019.2032 BL18-Jan-2008 $16,019.20$0.00
Rental201621-Nov-2014 06-140819PERTH$15,612.8032 BL18-Jan-2008 $15,612.80$0.00
Rental201522-Nov-2013 06-130741PERTH$15,216.0032 BL18-Jan-2008 $15,216.00$0.00
Rental201419-Nov-2012 06-117628PERTH$14,918.4032 BL18-Jan-2008 $14,918.40$0.00
Rental201316-Dec-2011 103955PERTH$14,512.0032 BL18-Jan-2008 $14,512.00$0.00
Rental201222-Dec-2010 88188PERTH$15,498.5632 BL18-Jan-2008 $15,498.56$0.00
Rental201109-Nov-2009 72096PERTH$15,178.2432 BL18-Jan-2008 $15,178.24$0.00
Rental201009-Dec-2008 59358PERTH$14,565.7632 BL18-Jan-2008 $14,565.76$0.00
Rental200923-Apr-2008 (REFUND) 45224PERTH$2,641.3232 BL18-Jan-2008 $14,087.04$0.00
Rental200927-Nov-2007 45224PERTH$16,728.36
Rental200823-Apr-2008 (REFUND) 32427PERTH$110.8838 BL06-Feb-2001 $8,316.00$0.00
Rental200819-Dec-2006 32427PERTH$8,426.88
Rental200713-Dec-2005 19007PERTH$3,853.9638 BL06-Feb-2001 $3,853.96$0.00
Rental200604-Feb-2005 7534PERTH$3,762.0038 BL06-Feb-2001 $3,762.00$0.00
Rental200515-Jan-2004 68095PERTH$3,653.3238 BL06-Feb-2001 $3,653.32$0.00
Rental200406-Feb-2003 57145PERTH$3,536.2838 BL06-Feb-2001 $3,536.28$0.00
Rental200330-Jan-2002 45024PERTH$3,444.3238 BL06-Feb-2001 $3,444.32$0.00
Rental200212-Feb-2001 (REFUND) 33074PERTH$150.4838 BL06-Feb-2001 $3,444.32$0.00
Rental200205-Feb-2001 33074PERTH$463.60
Rental200220-Jun-2000 1225KARRATHA$3,131.20

Expenditure

YearForm 5 TypeMin ExpdExp Lodged DateTotal ExpdExemp NoExemp LodgedExemp AmtExemp StatusOutcome DateExploration ActivitiesMining ActivitiesAboriginal SurveyRentAdministrationProspectingStrike Through
2018$96,000.00false
2017$96,000.0014-Mar-2017 $221,837.60$201,034.03$0.00$0.00$20,395.52$408.05$0.00false
2016$96,000.0011-Mar-2016 $50,548.1248303711-Mar-2016 $96,000.00Granted04-Apr-2016 $30,655.96$0.00$0.00$19,892.16$0.00$0.00false
2015$96,000.0013-Mar-2015 $57,644.0046387013-Mar-2015 $38,356.00Granted26-May-2015 $24,093.00$0.00$0.00$33,438.00$113.00$0.00false
2014$96,000.0028-Feb-2014 $107,170.00$88,450.00$0.00$0.00$18,400.00$320.00$0.00false
2013$96,000.0006-Mar-2013 $120,187.00$83,884.00$0.00$18,588.00$17,715.00$0.00$0.00false
2012$96,000.0007-Mar-2012 $22,468.0039289807-Mar-2012 $73,532.00Granted21-Jun-2012 $5,219.00$0.00$0.00$16,884.00$365.00$0.00false
2011$96,000.0011-Mar-2011 $18,653.0036754814-Mar-2011 $77,347.00Granted31-May-2011 $3,906.00$0.00$0.00$14,382.00$365.00$0.00false
2010$96,000.0005-Mar-2010 $40,698.0034255112-Mar-2010 $55,302.00Granted25-Nov-2010 $24,407.00$0.00$0.00$16,291.00$0.00$0.00false
2009$96,000.0010-Mar-2009 $119,764.00$106,022.00$0.00$1,249.00$12,493.00$0.00$0.00false
2008$76,000.0007-Mar-2008 $118,492.00$95,811.00$0.00$3,365.00$16,994.00$2,322.00$0.00false
2007$47,334.0002-Mar-2007 $198,492.00$151,212.00$0.00$34,335.00$9,325.00$3,620.00$0.00false
2006$34,200.0008-Mar-2006 $171,379.00$131,103.00$0.00$28,955.00$5,321.00$6,000.00$0.00false
2005$34,200.0023-Mar-2005 $48,809.00$36,932.00$0.00$0.00$5,077.00$6,800.00$0.00false
2004$34,200.0023-Mar-2004 $168,562.00$126,794.00$0.00$30,000.00$4,968.00$6,800.00$0.00false
2003$34,200.0028-Mar-2003 $40,652.00$28,246.00$0.00$0.00$5,606.00$6,800.00$0.00false
2002$34,200.0005-Apr-2002 $29,738.0015860803-Apr-2002 $4,462.00Granted27-May-2002 $0.00$0.00$0.00$0.00$0.00$0.00false

Bond

Bond NumberNameSuretyAmountBond DateStatusStatus DateTypeCeasedOther Affected Tenements
385306Bond Requirement$62,000.0016-Nov-2011 Finalised27-Oct-2014 Unconditional Performance Bondtrue
385089Bond - Unconditional Performance BondAUSTRALIA AND NEW ZEALAND BANKING GROUP LTD$62,000.00 (Inital)11-Nov-2011 Retired - MRF27-Oct-2014 Unconditional Performance Bondtrue
307533Bond Requirement$34,000.0007-May-2007 Finalised17-Nov-2011 true
261237Bond - Unconditional Performance BondAUSTRALIA AND NEW ZEALAND BANKING GROUP LTD$34,000.00 (Inital)01-Mar-2007 Retired17-Nov-2011 Unconditional Performance Bondtrue

Native Title Referrals

Referred to Native Title DateReferral TypeCurrent StatusProcedureDetailsObjectionsWater CommentsDetermination AreasClaimsRepresentative Area Bodies
Tenement Application