Extracted from MTO on 23-Jan-2021 03:45,
last changed 16-Jan-2021.
# | Ver | Text | Start | End |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 21-Feb-2017 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 21-Feb-2017 | |
3 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 21-Feb-2017 | |
4 | 1 | No interference with Geodetic Survey Stations ROUND, R6 and L5 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 21-Feb-2017 | |
5 | 1 | No interference with the use of the Aerial Landing Ground and mining thereon being confined to below a depth of 15 metres from the natural surface. | 21-Feb-2017 | |
| 1 | Consent to explore on Meda Location 15 (Yampi Defence Training Area) granted subject to: | 21-Feb-2017 | |
6 | 1 | The Australian Government not guaranteeing access to the Commonwealth Land. | 21-Feb-2017 | |
7 | 1 | The licensee obtaining the relevant approvals required under the Land Acquisitions Act 1989 (Cth). | 21-Feb-2017 | |
8 | 1 | If deed of access is granted, exploration activities being limited to those specified in the deed. | 21-Feb-2017 | |
9 | 1 | Any proposed future mining activities, being subject to separate approval required under the Lands Acquisition Act 1989 (Cth). | 21-Feb-2017 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 21-Feb-2017 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 21-Feb-2017 | |
3 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 21-Feb-2017 | |
4 | 1 | No interference with Geodetic Survey Stations ROUND, R6 and L5 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 21-Feb-2017 | |
5 | 1 | No interference with the use of the Aerial Landing Ground and mining thereon being confined to below a depth of 15 metres from the natural surface. | 21-Feb-2017 | |
| 1 | Consent to explore on Meda Location 15 (Yampi Defence Training Area) granted subject to: | 21-Feb-2017 | |
6 | 1 | The Australian Government not guaranteeing access to the Commonwealth Land. | 21-Feb-2017 | |
7 | 1 | The licensee obtaining the relevant approvals required under the Land Acquisitions Act 1989 (Cth). | 21-Feb-2017 | |
8 | 1 | If deed of access is granted, exploration activities being limited to those specified in the deed. | 21-Feb-2017 | |
9 | 1 | Any proposed future mining activities, being subject to separate approval required under the Lands Acquisition Act 1989 (Cth). | 21-Feb-2017 | |
Type | Number | Details |
Application to Amend | 505184 | Lodged:11:59:04 24 April 2017Amending:Address (Including DTC Details)From:Principal Place of Business : PALADIN ENERGY MINERALS NL, SAME AS CORRESPONDENCE and DTC :PALADIN ENERGY MINERALS NL, PO BOX 201, SUBIACO, WA, 6904To:Principal Place of Business : PALADIN ENERGY MINERALS NL, PO BOX 128, DIANELLA, WA, 6059, xxxxxxxx@bigpond.com and DTC :PALADIN ENERGY MINERALS NL, HELEN SYMES TENEMENT CONSULTING, PO BOX 128, DIANELLA, WA, 6059, xxxxxxxx@bigpond.comRECORDED:11:59:04 24 April 2017 |
Forfeiture | 534761 | Initiated:20/07/2018 for non-compliance with reporting requirementsRECORDED:15:57:40 10 July 2018Notice Issued:Regulation 50 Notice sent 20/07/2018 for non-compliance with reporting requirements pursuant to Sec 115A.Compliance Date:24/08/2018WITHDRAWN:07 August 2018 (Report previously submitted incorrectly) |
Mortgage | 558273 | Lodged:12:34:27 11 July 2019Mortgaged Shares:100/100 shares JACKSON CAGE PTY LTDMortgagee:MARENICA ENERGY LTDREGISTERED:12:34:27 11 July 2019 |
Caveat | 558274 | Lodged:12:34:27 11 July 2019Caveat Type:Absolute CaveatCaveator:MARENICA ENERGY LTDShares Caveated:100/100 shares JACKSON CAGE PTY LTDREJECTED:12:34:27 11 July 2019Relodged:14:35 11 October 2019Caveat Type:Absolute CaveatCaveator:MARENICA ENERGY LTDShares Caveated:100/100 shares JACKSON CAGE PTY LTDRECORDED:14:35 11 October 2019 |
Caveat | 566643 | Lodged:08:30 15 November 2019Caveat Type:Consent CaveatCaveator:ORANO AUSTRALIA PTY LTDShares Caveated:100/100 shares JACKSON CAGE PTY LTDRECORDED:08:30 15 November 2019 |
Application to Amend | 573374 | Lodged:15:46:47 03 March 2020Amending:Address (Including DTC Details)From:Principal Place of Business : JACKSON CAGE PTY LTD, JACKSON CAGE PTY LTD, SUITE 403, GOLDFIELD HOUSE, 1 ALFRED STREET, SYDNEY, NSW, 2000, xxxxxxxxx@optmining.com.au, xxxxxxxxx809 and DTC :JACKSON CAGE PTY LTD, HELEN SYMES TENEMENT CONSULTING, PO BOX 128, DIANELLA, WA, 6059, xxxxxxxx@bigpond.com, xxxxxxx624To:Principal Place of Business : JACKSON CAGE PTY LTD, JACKSON CAGE PTY LTD, OFFICE C1, 1139 HAY STREET, WEST PERTH, WA, 6005, xxxxxxx@mcbain.id.au, xxxxxxx846 and DTC :JACKSON CAGE PTY LTD, GILLIAN MCBAIN, PO BOX 2071, WARWICK, WA, 6024, xxxxxxx@mcbain.id.au, xxxxxxx846RECORDED:15:46:47 03 March 2020 |
Application to Amend | 573378 | Lodged:16:03:26 03 March 2020Amending:Address (Including DTC Details)From:Principal Place of Business : JACKSON CAGE PTY LTD, JACKSON CAGE PTY LTD, OFFICE C1, 1139 HAY STREET, WEST PERTH, WA, 6005, xxxxxxx@mcbain.id.au, xxxxxxx846 and DTC :JACKSON CAGE PTY LTD, GILLIAN MCBAIN, PO BOX 2071, WARWICK, WA, 6024, xxxxxxx@mcbain.id.au, xxxxxxx846To:Principal Place of Business : JACKSON CAGE PTY LTD, OFFICE C1, 1139 HAY STREET, WEST PERTH, WA, 6005, xxxxxxxxxxxxx@marenicaenergy.com.au, xxxxxxxxx816 and DTC :JACKSON CAGE PTY LTD, HELEN SYMES TENEMENT CONSULTING, PO BOX 128, DIANELLA, WA, 6059, xxxxxxxx@bigpond.com, xxxxxxx624RECORDED:16:03:26 03 March 2020 |
Application to Amend | 573379 | Lodged:16:03:26 03 March 2020Amending:Address (Including DTC Details)From:JACKSON CAGE PTY LTD, HELEN SYMES TENEMENT CONSULTING, PO BOX 128, DIANELLA, WA, 6059, xxxxxxxx@bigpond.com, xxxxxxx624To:JACKSON CAGE PTY LTD, GJM MINING TITLE SERVICES, PO BOX 2071, WARWICK, WA, 6024, xxxxxxx@mcbain.id.au, xxxxxxx846RECORDED:16:03:26 03 March 2020 |